- What the law says
- Who should read this
- What must the risk register contain?
- How are likelihood and impact scored?
- What does the risk appetite statement say?
- How do a board and an audit committee read the quarterly risk report?
- What do a lender and a donor ask for?
- How does the register link to the continuity plan, the compliance register and the incident register?
- How is the register controlled as a document?
- Common faults and fixes
- Worked example: Kilimanjaro Cold Logistics Limited, December 2026
- Mainland and Zanzibar: which rules differ?
- What to do now
- Key dates
- What the NEMBO desk prepares
- How Zatra helps
- Sources and status
- Frequently asked questions
What must a risk register contain in Tanzania?
A Tanzanian risk register lists each risk as a cause, an event and a consequence, scores likelihood and impact before and after controls on a board-approved scale, names one owner per row. It records the controls and dated actions, and carries a version, a review date and a comparison with the board's risk appetite. A quarterly risk report summarises movement and the rows outside appetite for the board.

What the law says
No Tanzanian statute prescribes the layout of a risk register; the duty to keep one comes from directors' law, regulators, standards and funders. A risk register is the controlled list of the risks a company faces, each with a cause, a consequence, a score, an owner, the controls in place and the actions still open. The quarterly risk report is the summary a board reads from it.
For a private company the starting point is the Companies Act, Cap. 212, read on TanzLII. The Act places management in the hands of the directors and sets their general duties: good faith in the company's best interests, a proper purpose, and the care a reasonably diligent person in that position would bring. The 2023 revised edition renumbered the sections, so this guide names no pinpoint section. A Zatra note of 10 October 2026 reads the good faith duty at s.185 and the care duty at s.188 of R.E. 2023; confirm against the revised text.
For a bank or financial institution the Bank of Tanzania's Risk Management Guidelines for Banks and Financial Institutions, 2010 make the board ultimately responsible for the level of risk taken (paragraph 1.5.2.1). They require a risk management programme covering credit, liquidity, market, operational, strategic and compliance risk, reviewed at least annually (1.3.1). The Banking and Financial Institutions (Corporate Governance) Regulations, 2021, GN No. 767 of 29 October 2021, add that the board oversees risk management (regulation 22), reviews risk policies and exposure limits at least once a year (regulation 31) and receives reports of breaches of risk limits (regulation 45).
For a listed company the Capital Markets and Securities Authority's Guidelines on Corporate Governance Practices by Public Listed Companies in Tanzania, 2002 ask the board to define a risk policy and identify the principal risks and the measures to manage them (paragraph 4.1.1). The board reviews internal control regularly (4.1.1(v)) and establishes an audit committee of at least three independent non-executive directors (4.5.1). The annual report states compliance (paragraph 1.7).
For a certified company, ISO 9001:2015 clause 6.1, actions to address risks and opportunities, requires the organisation to determine the risks and opportunities that bear on its quality management system, plan proportionate actions and evaluate them. ISO published ISO 9001:2026 on 16 September 2026 and now lists the 2015 edition as withdrawn; the ISO announcement promises greater clarity on the consideration of risks and opportunities. ISO 31000:2018, Risk management: Guidelines supplies the vocabulary most registers borrow and cannot be certified against.
Who should read this
The managing director or company secretary asked for "the risk register" by a board, an auditor or a certification body. The finance manager writing the risk section of a loan or grant application, the quality manager preparing an ISO 9001 audit, the head of risk at a bank or microfinance institution, and the NGO programme manager whose donor asks for a risk matrix. A sole trader with no board, lender or certification can skip it.
What must the risk register contain?
A register is a table. Every row is one risk, and every column answers a question a reader will ask. The columns below are common to the Bank of Tanzania guidelines, the ISO 31000 process steps and the Orange Book, HM Treasury's guidance on risk updated 18 November 2026.
| Column | What goes in it |
|---|---|
| Risk (event) and cause | What could happen and why, in one line each; controls are built against causes |
| Consequence | What it costs: money, people, licence, reputation |
| Category | Strategic, operational, financial, compliance, people, technology, safety |
| Inherent likelihood and impact | Scores 1 to 5 before controls: the exposure if controls fail |
| Existing controls | The named procedure, contract, cover or system the auditor will test |
| Residual likelihood and impact | Scores 1 to 5 after controls: the number compared with appetite |
| Owner | One named post holder; a committee cannot own a risk |
| Actions | What more will be done, by whom, by when |
| Review date and movement | Next re-score date; up, down or flat since last quarter |
The Orange Book states the discipline plainly: risk is expressed in terms of causes, potential events and their consequences. A register that lists symptoms ("cash is tight") instead of events ("the anchor customer pays 90 days late") cannot be scored or owned. Under ISO 9001 the register also needs an opportunities view: clause 6.1 pairs risks with opportunities, and the 2026 edition separates the two with sub-clauses 6.1.1 to 6.1.3, according to the DNV transition note read on 26 November 2026.
How are likelihood and impact scored?
Most Tanzanian registers use a 5 by 5 matrix: likelihood 1 to 5 multiplied by impact 1 to 5, giving a score of 1 to 25. The board approves the scales once, in the risk management policy. An illustrative likelihood scale runs from 1 (rare, less than once in 10 years) to 5 (more than once a year). An illustrative impact scale runs from 1 (below TZS 10,000,000, no injury) to 5 (above TZS 500,000,000, a fatality or loss of licence). Neither ISO 9001 nor ISO 31000 prescribes a matrix or a register; the Chartered Quality Institute's note on clause 6.1 records that the standard does not prescribe a methodology, only that the response is proportionate.
The bands then set the response. A common convention is 1 to 4 low (accept and monitor), 5 to 9 moderate (owner manages), 10 to 15 high (board sees it quarterly with an action plan) and 16 to 25 extreme (immediate action, chair informed between meetings). Inherent and residual scores both appear: the inherent score answers the auditor's "what if the control fails", the residual score answers the board's "where are we today".
What does the risk appetite statement say?
The appetite statement is the board's one-page instruction on how much risk the company will carry, by category. The Bank of Tanzania regulations refer to the risk appetite approved by the board (regulations 23 and 44) without defining a form; the IIA's Three Lines Model places setting appetite with the governing body. HM Treasury's Risk Appetite Guidance Note of August 2021 gives a five-level scale from averse to eager and asks each statement to say whether it applies to the inherent or the residual score.
A workable statement has three parts. First, a sentence per category: "averse to safety and compliance risk, cautious on financial risk, open on growth risk". Second, a residual ceiling per category, for example 9 for compliance and safety, 12 for financial and 15 for strategic. Third, the escalation rule: any score above the ceiling appears on the quarterly report with a dated action, and any extreme score reaches the chair within 48 hours.
How do a board and an audit committee read the quarterly risk report?
A board does not read a 60-row register. It reads a quarterly risk report built from it; the audit committee reads the register itself. The CMSA guidelines expect audit committee members to be informed, vigilant and effective overseers of the financial reporting process and internal controls (paragraph 4.5.3). The Bank of Tanzania guidelines ask for credit risk reviews at least quarterly, reported to the board or its sub-committee (paragraph 2.5.1.1). For a private company the report slots into the board pack.
Page one carries the heat map (each risk plotted at its residual position), the count per band, the top five risks against appetite and the movement since last quarter. Page two carries one paragraph per risk outside appetite: what changed, what the owner did, what remains, and the decision the board is asked to make.
What do a lender and a donor ask for?
A credit committee asks for the risk section of the business plan and reads it beside the sensitivity analysis, the cash flow forecast and the security. The plan an investor reads and the sensitivity analysis a lender tests are the two places the register feeds. This guide read no Tanzanian bank's risk assessment page and states no bank term.
Donor templates are explicit. The European Commission's Horizon Europe application form, Part B version 5.1 of 22 January 2026, carries table 3.1e, critical risks for implementation: each risk with likelihood and severity rated low, medium or high, the work package involved, and the proposed risk-mitigation measures. The register carries a conversion note so the same risk is scored once and translated for each funder, and the donor project report updates the matrix each period.
How does the register link to the continuity plan, the compliance register and the incident register?
The risk register is the parent document; three others hang from it. The business continuity plan takes the risks whose consequence is "operations stop" (power, flood, fire, system failure) and writes the recovery procedure; ISO 22301:2019 lists ISO 31000 as a related standard. The compliance register takes the risks whose consequence is a penalty, a licence condition or a prosecution and lists every obligation, its authority, its due date and its evidence; the compliance calendar is its dated view.
The incident register runs the other way. It records what did happen: accidents under the Occupational Health and Safety Act, Cap. 297 (see the accident register guide), complaints, fraud, data breaches and near misses. Every incident is checked against the risk register: if the risk was listed, the likelihood is reviewed; if not, a new row opens.
How is the register controlled as a document?
The register is a controlled document; the controlled documents guide gives the mechanics.
- Owner: one post, usually the risk and compliance manager, the finance manager or the company secretary, who alone issues the register.
- Version and date: a version per quarter (for example v2026.4), the issue date and the meeting that received it. Superseded versions are kept for the period in the retention guide.
- Review cycle: owners re-score monthly or quarterly; management reviews the register quarterly and the board annually.
- Approval trail: the policy, appetite and scales are approved by board resolution; each quarterly register is minuted. The delegation of authority matrix says who may accept a risk outside appetite pending the next meeting.
- Evidence: each named control points to an SOP, a contract, an insurance policy or a system report an auditor can open.
Common faults and fixes
| Fault | What the reader concludes | Fix |
|---|---|---|
| No owner, or "management" as owner | Nobody will act | One named post per row |
| Only one score, no residual | Controls were never valued | Score before and after controls |
| Same scores for four quarters | Copied forward, not reviewed | Owner re-scores each quarter; add a movement column |
| Symptoms listed as risks | Causes were not analysed | Rewrite each row as cause, event, consequence |
| No version or date | Cannot tell which register the board saw | Version, date and meeting reference on every issue |
Worked example: Kilimanjaro Cold Logistics Limited, December 2026
Kilimanjaro Cold Logistics Limited is a fictional Moshi company running a 1,200-pallet cold store and six refrigerated trucks to Dar es Salaam, with a three-person board, a bank term loan and an ISO 9001 surveillance audit due in February 2027. Every figure below is illustrative. The board approved residual ceilings of 9 for safety and compliance, 12 for operational and financial, and 15 for strategic risk.
Register extract, Q4 2026, version v2026.4, reviewed 20 November 2026
| Ref | Risk and cause | Consequence (illustrative) | Inherent L x I | Key controls | Residual L x I | Owner and open action |
|---|---|---|---|---|---|---|
| R-01 | Cold store power loss over six hours; grid outage with generator fault | Spoilage up to TZS 850,000,000 | 4 x 5 = 20 | Standby generator, fuel contract, temperature alarms | 2 x 4 = 8 | Operations Manager; second generator by 31 January 2027 |
| R-02 | Loss of anchor customer; re-tender of its cold chain in 2027 | 40 per cent of revenue, TZS 2,400,000,000 a year; covenant breach | 3 x 5 = 15 | Monthly service level report; contract to 30 June 2028 | 3 x 4 = 12 | Managing Director; two new accounts by 31 March 2027 |
| R-03 | Reefer truck failure in transit; ageing fleet, no spare | Rejected consignment, claim up to TZS 60,000,000 | 4 x 3 = 12 | Preventive maintenance; GPS temperature logging | 2 x 3 = 6 | Fleet Manager; spare reefer by 28 February 2027 |
| R-04 | Late VAT return and EFD gaps; one accountant, manual capture | Penalties and interest; tax clearance delay | 3 x 3 = 9 | Compliance calendar; second reviewer before filing | 1 x 3 = 3 | Finance Manager; VFD integration by 31 January 2027 |
| R-05 | Ransomware on the warehouse system; unpatched server, shared passwords | Three days without dispatch, TZS 45,000,000 lost margin | 3 x 4 = 12 | Daily off-site backup; multi-factor login | 2 x 4 = 8 | ICT Officer; restore test by 15 December 2026 |
| R-06 | Ammonia leak in the plant room; valve corrosion, no gas detector | Injury; OSHA stop order | 2 x 5 = 10 | Annual pressure inspection; PPE; evacuation drill | 1 x 5 = 5 | HSE Officer; gas detectors by 31 December 2026 |
Quarterly movement, Q3 2026 to Q4 2026
| Ref | Residual Q3 2026 | Residual Q4 2026 | Movement | Against appetite |
|---|---|---|---|---|
| R-01 | 12 | 8 | Down: generator serviced, alarms installed | Within (ceiling 12) |
| R-02 | 12 | 12 | Flat: no new accounts signed | Within (ceiling 15), watch |
| R-03 | 9 | 6 | Down: maintenance contract signed | Within (ceiling 12) |
| R-04 | 6 | 3 | Down: calendar and second reviewer in place | Within (ceiling 9) |
| R-05 | New | 8 | New after an October phishing attempt | Within (ceiling 12) |
| R-06 | 10 | 5 | Down: inspection done, drill held | Within (ceiling 9); outside in Q3 |
The report tells the board three things in a minute. R-06 was outside appetite in Q3 and is now inside, with the action that moved it. R-02 is the largest unresolved exposure and has not moved, so the board asks for a dated sales plan rather than another quarter of "watch". R-05 is new, and with the TZS 120,000,000 second generator under R-01 it explains two lines in the January budget.
Mainland and Zanzibar: which rules differ?
The register itself does not change between Mainland and Zanzibar; the law behind the duty does. The Companies Act, Cap. 212, and BRELA apply on the Mainland. Zanzibar companies are registered with the Business and Property Registration Agency under Zanzibar's own Companies Act, which this guide did not read, so the directors' duties it imposes are unconfirmed here and a Zanzibar advocate should be asked. The Bank of Tanzania instruments are drafted for all licensed institutions, and a Zanzibar-licensed institution should confirm with its supervisor that nothing local is added. Whether the CMSA guidelines reach a Zanzibar issuer was not confirmed. ISO 9001 and ISO 31000 do not distinguish between the two, and donor and lender templates apply on both sides.
What to do now
- Fix the framework: have the board approve the risk management policy, the 5 by 5 scales, the bands and the appetite ceilings by resolution.
- Run a risk workshop: with the heads of function, list events by cause and consequence across every category; aim for 15 to 30 rows.
- Score twice: give each row an inherent and a residual score, and name the control that explains the difference.
- Assign owners and actions: one post per row, one dated action per row outside appetite, and a review date.
- Reconcile the registers: match the risk register to the incident register, the compliance register and the continuity plan.
- Issue version one: under document control, with a version number, date and meeting reference, filed with the board pack.
- Report quarterly: a heat map, top risks against appetite, movement and overdue actions, minuted at each board meeting.
- Review annually: re-approve the policy, scales and appetite, and map the register to clause 6.1 of the ISO 9001 edition the certification body audits against.
Key dates
Owners re-score monthly or quarterly; the board receives the quarterly report at each meeting and re-approves the policy and appetite once a year. Banks review risk policies and exposure limits at least annually under regulation 31 of the 2021 regulations and credit risk at least quarterly under the 2010 guidelines. ISO 9001:2026 was published on 16 September 2026; the DNV note read on 26 November 2026 reports a three-year transition, with 2015 certificates ceasing to be valid after 30 September 2029, a date to confirm with the certification body. The free reporting framework tool and the answers page place the register in the annual reporting calendar.
What the NEMBO desk prepares
The policies and SOPs desk prepares the risk management policy, the appetite statement, the scoring scales, the register in a controlled spreadsheet with inherent and residual columns and a heat map, the quarterly risk report template and the adopting board resolution. Zatra Consultants researches and drafts the content; Dennis Wilson reviews the systems beat and checks every clause and regulation reference against the text. NEMBO designs and delivers the documents, and where a client runs its register in a system the systems desk builds the workflow. The process page shows the steps; start here shares the details.
Two cost buckets apply: government, bank or regulator charges are paid at the official rate and are separate from NEMBO's and Zatra's fees, which are published on the packages page and quoted in writing. NEMBO does not decide or guarantee any authority's outcome.
How Zatra helps
Zatra's internal controls and risk advisory service runs the risk workshop, scores the register with management and tests the named controls. Its corporate governance advisory service drafts the board and audit committee charters and the appetite statement, and its business process and SOP consulting service writes the procedures the controls column points to. Two NEMBO insights sit beside this one: the controlled documents guide and the delegation of authority matrix. CPA Altho Mwangoa signs any tax computation or audited figure that a financial risk row relies on. Disputes, prosecutions, formal legal opinions on directors' liability and anything before a court, tribunal, the CMA or a registry go to an advocate.
Risk register and risk policy set
Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.
Open the desk pageSources and status
Accurate as at 26 November 2026. Read in full: the ISO catalogue pages for ISO 31000:2018, ISO 9001:2015 and ISO 9001:2026, the ISO announcement of 16 September 2026, the CMSA guidelines of 2002. Also read in full: the Banking and Financial Institutions (Corporate Governance) Regulations, 2021, the IIA Three Lines Model and the HM Treasury Risk Appetite Guidance Note. Read in part: the Bank of Tanzania Risk Management Guidelines, 2010 (sections 1 to 5), the Orange Book and the Companies Act on TanzLII (the directors' duties sections were not reached, so no pinpoint section is quoted). The ISO 9001:2026 transition deadline and the sub-clause structure of clause 6.1 rest on a DNV note and a third-party summary, not on the standard's text.
- 1ISO 31000:2018, Risk management: GuidelinesISO, February 2018, confirmed 2023. Accessed 26 November 2026.
- 2ISO 9001:2015, Quality management systems: RequirementsISO, September 2015. Accessed 26 November 2026.
- 3ISO 9001:2026, Quality management systems: RequirementsISO, 16 September 2026. Accessed 26 November 2026.
- 4ISO launches update to world's most widely used quality management standardISO, 16 September 2026. Accessed 26 November 2026.
- 5Risk Management Guidelines for Banks and Financial Institutions, 2010Bank of Tanzania, August 2010. Accessed 26 November 2026.
- 6The Banking and Financial Institutions (Corporate Governance) Regulations, 2021Bank of Tanzania, GN No. 767 of 29 October 2021 (ECGI copy). Accessed 26 November 2026.
- 7Guidelines on Corporate Governance Practices by Public Listed Companies in TanzaniaCapital Markets and Securities Authority, 2002 (ECGI copy). Accessed 26 November 2026.
- 8Companies Act, 2002 (Cap. 212)TanzLII, version in force from 1 July 2016. Accessed 26 November 2026.
- 9The IIA's Three Lines Model: An update of the Three Lines of DefenseInstitute of Internal Auditors, July 2020, updated September 2024. Accessed 26 November 2026.
- 10The Orange Book: Management of Risk, Principles and ConceptsHM Treasury, 20 August 2025, updated 18 November 2026. Accessed 26 November 2026.
Figures to confirm before you act
- Companies Act R.E. 2023 section numbers for the good faith duty (s.185) and the care duty (s.188) are taken from a Zatra note of 10 October 2026, not read in the revised text this session.
- ISO 9001:2026 transition: the 30 September 2029 end of validity for 2015 certificates and the 6.1.1 to 6.1.3 sub-clause structure rest on a DNV note and a third-party summary; confirm with the certification body and the standard's text.
- Bank of Tanzania Risk Management Guidelines, 2010: sections 6 to 8 (strategic risk, compliance risk, inherent risk mapping) were not read; paragraph numbers cited are from sections 1 to 5.
- CMSA guidelines of 2002 were read from the ECGI-hosted copy; the operative date is blank in that copy and the cmsa.go.tz page was not read.
- Whether the CMSA guidelines and the BoT regulations apply unchanged to Zanzibar-incorporated issuers and Zanzibar institutions was not confirmed; Zanzibar's Companies Act and occupational safety law were not read.
- Illustrative figures: TZS 850,000,000 stock at risk, TZS 2,400,000,000 anchor revenue, TZS 60,000,000 claim per trip, TZS 45,000,000 lost margin, TZS 120,000,000 generator, the 5 by 5 scales, bands and appetite ceilings are examples, not benchmarks.
- Lender terms: no Tanzanian bank's published risk assessment page was read; the lender section states no bank requirement.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
How many risks should a Tanzanian SME register hold?
Enough to cover each function once, rarely more than 30 rows for a company under 100 staff, with the board report showing the top 10. A register past 50 rows usually mixes risks with tasks and hazards; move hazards to the safety risk assessment and tasks to the action log.
Does ISO 9001 require a risk register?
No. Clause 6.1 requires the organisation to determine risks and opportunities, plan proportionate actions and evaluate them, keeping whatever evidence it chooses. A register is the common evidence because an auditor can trace a row to a control and an action; another method must show the same chain.
Who maintains the register in a company with no risk manager?
The finance manager or company secretary holds the document, each head of function owns the rows for their area, and the managing director signs the quarterly report. The external auditor's management letter and the certification body's findings act as the independent check a larger company gets from internal audit.
Can the register live in a spreadsheet?
Yes, if it is treated as a controlled document: one master file, a version number and date on every issue, a read-only copy in the board pack and previous versions archived. A system earns its cost once several sites score rows or a regulator asks for an audit trail of score changes.
What is the difference between a risk register and an issue log?
A risk is something that may happen; an issue is something that has happened and needs a response now. When a registered risk occurs it is logged as an incident or issue and the risk row is re-scored. Mixing the two makes the heat map show past events as future exposure.
How is reputational risk scored when there is no money figure?
Score impact on the non-financial side of the scale: a regulator query, a lost tender, a public complaint, a licence condition. Write the consequence as the event that costs reputation, such as a product recall, and attach the revenue or contract at stake where one exists.
What does a certification auditor ask for at a surveillance visit?
The current register and the previous version, the minute or management review record that received each, the scoring method, the evidence behind a sample of controls, and proof that actions closed on time. The auditor also tests whether new risks appeared after a new site, product or lost customer.
Does a donor-funded project need its own register?
Usually yes, because the donor's template, scale and reporting period differ from the company's. Keep the project register as a child of the corporate register: the same event is scored once on the corporate scale, translated to the donor's labels, and reported with the mitigation measures the application promised.