Sources and uses of funds Tanzania: the funding plan a lender, TISEZA and an investor read before anything else in the business plan

The first financial page a lender, TISEZA or an investor turns to is the sources and uses table. This guide sets out what the uses column must cost and evidence, how much equity Tanzanian banks publish as the floor, the TISEZA and ZIPA capital thresholds, the 7 to 3 debt-to-equity test in the Income Tax Act, the Bank of Tanzania registration of foreign loans, and a worked example on a TZS 2,400,000,000 agro-processing plant with the debt service cover arithmetic.

CPA Altho MwangoaChief Financial Officer, Zatra Consultants Limited
18 November 2026Published
24 November 2026Updated
19 min4,096 words
On this page
  1. What the law says
  2. Who should read this
  3. What goes in the uses column?
  4. What goes in the sources column, and how much equity is enough?
  5. How does TISEZA read the funding plan?
  6. Worked example: a TZS 2,400,000,000 agro-processing plant
  7. Which documents evidence each source?
  8. What does ZIPA ask for in Zanzibar?
  9. What to do now
  10. Key dates
  11. What the NEMBO desk prepares
  12. How Zatra helps
  13. Sources and status
  14. Frequently asked questions
Quick answer

What must a sources and uses of funds statement show in Tanzania?

A sources and uses of funds Tanzania lenders and TISEZA read lists every project cost to the first revenue month, with a dated quotation behind each line, against the equity, quasi-equity and debt that will pay for it, each evidenced and conditioned. Equity must meet the lender's published floor, 25 to 40 percent on the pages read, and the capital must meet the TISEZA or ZIPA threshold.

Cover: business plan with the sources and uses of funds table for a Tanzanian agro-processing project

What the law says

A sources and uses of funds Tanzania lenders and TISEZA ask for is one table: on the left, every cost the project will incur to the day it earns revenue; on the right, every shilling and dollar that will pay for it. No statute prescribes the table, but four bodies of law decide what must be in it. The TISEZA certificate of incentives page lists among its required documents a project business plan and evidence of sufficient finance capital to implement the project. It sets the minimum investment at USD 500,000 for a wholly foreign-owned or joint venture project and USD 50,000 for a project wholly owned by Tanzanian citizens. The Zatra fee register records the gazetted shilling equivalents, TZS 1,500,000,000 and TZS 150,000,000, under regulation 14 of the Investment and Special Economic Zones Regulations, 2025 (TZ-02). Section 3 of the Investment and Special Economic Zones Act, 2025 defines capital to include cash, plant, machinery, equipment, land and other assets likely to last more than twelve months, which is the definition the uses column must follow.

The second body is bank regulation. The Banking and Financial Institutions (Management of Risk Assets) Regulations, 2014 require every bank to lend under a written credit policy. The Credit Concentration and Other Exposure Limits Regulations, 2014 (GN 288 of 2014) cap credit to a single borrower and its related parties at 25 percent of the bank's core capital where fully secured, 10 percent where partly secured and 5 percent where unsecured. A project whose loan exceeds one bank's limit needs a syndicate, and the sources column must say so.

The third is tax. Section 12(2) of the Income Tax Act, Cap. 332 caps deductible interest for an exempt-controlled resident entity at the interest on a debt-to-equity ratio of 7 to 3, and section 12(3) makes an entity exempt-controlled where 25 percent or more of its underlying ownership is held by non-residents, exempt persons or their associates. Section 33A, inserted by the Finance Act 2025, deems 15 percent of profit undistributed twelve months after year end to be distributed (F0202), which reaches a plan that funds expansion from retained earnings. The fourth is exchange control. Regulation 25 of the Foreign Exchange Regulations, 2022 requires a foreign loan with a tenure above 365 days to be registered with the Bank of Tanzania, assigns a Debt Registration Number before disbursement and debt service, and charges TZS 1,000,000 a day for late filing. Zatra's note on lending to a Tanzanian company from abroad covers that filing. This guide covers the table.

Who should read this

This guide is for the promoter of a Mainland or Zanzibar project seeking a term loan, a TISEZA certificate, a ZIPA certificate or an equity partner, and for the finance manager or CPA who builds the plan. It also serves a Fursa365 match that has been offered a stake and wants to read the funding plan the way a credit committee does. The NEMBO notes on how investors read a business plan and the financial model assumptions investors challenge cover the chapters around this one.

What goes in the uses column?

The uses column is a cost schedule to the first month of revenue, not a wish list. Each line carries a basis: a pro-forma invoice, a bill of quantities, a valuation or a quotation, dated and in the currency of the supplier. CRDB's agri MSME products page states that plant and machinery loans for agro-processors are financed up to 60 percent of the pro-forma invoice value, so the invoice is the evidence the bank will read, not the plan's estimate.

What goes in the uses column?
Uses lineWhat it includesEvidence attachedTax or regulatory note
Land and sitePremium, survey, registration, title or derivative right, accessOffer letter, valuation, Commissioner for Lands assessmentPremium 0.25 percent of land value (F0459); title registration 50 percent of land rent (F0462)
Buildings and civil worksConstruction, utilities connection, permitsBill of quantities, contractor quotation, building permitClass 6 buildings 5 percent straight line (TRA Glance 2025/2026)
Plant, machinery and equipmentEquipment, freight, insurance, customs, installation, commissioningPro-forma invoices, Incoterm, duty computationClass 2 plant in agriculture or manufacturing 25 percent reducing balance; Class 8 agricultural plant 100 percent (TRA Glance)
VehiclesTrucks, pick-ups, forkliftsDealer quotationsCRDB truck loans at 25 percent equity with a chattel mortgage
Pre-operating costsStudies, licences, legal, TISEZA fee, training, recruitmentFee schedule with register IDsTISEZA certificate fee TZS 4,000,000 local or 6,000,000 foreign or JV (TZ-01)
Working capitalRaw materials, wages, utilities and overheads to the cash break-even month13-week forecast extended to twelve monthsVAT on inputs recoverable only once registered and fiscalised
Interest during constructionInterest on drawn debt before revenueDrawdown scheduleCapitalised or expensed per the accounting policy
ContingencyStated percentage of the physical cost linesRisk registerNo source read for this guide prescribes a percentage; lenders test the basis

Two lines are omitted more often than any other. Working capital is the first, because promoters cost the factory and forget the first three months of raw material. Interest during construction is the second. A lender that sees both will believe the rest of the table. The NEMBO note on the 13-week cash forecast shows how the working capital line is derived.

What goes in the sources column, and how much equity is enough?

The sources column lists equity, quasi-equity and debt, each with its provider, amount, currency, status and conditions. Status matters: committed equity sits in a bank account or a signed subscription agreement; a term sheet is a conditional source; a conversation is not a source. The bank pages read for this guide fix the equity floor by product.

What goes in the sources column, and how much equity is enough?
Source and providerPublished own-contribution ruleTenor and graceSource read
CRDB Bank, investment financingEquity contribution not less than 25 to 35 percent on an asset loan6 to 60 months or more; grace up to one year; TZS 1,000,000 to 5,000,000,000CRDB investment financing page
CRDB Bank, agro-processing plant and machineryMinimum contribution of 40 percent; financed up to 60 percent of the pro-forma invoice value36 to 120 monthsCRDB agri MSME products page
TADB, strategic and agro-processing projectsLoan not to exceed 75 percent of project cost1 to 15 years; grace not above 2 years; repayment per actual cash flowTADB strategic projects page (Swahili)
TIB Development Bank, industrial financingNo percentage printedGrace during construction and machinery import; loan in the revenue currencyTIB site (Swahili)
Foreign loan, parent or DFILender's own rulesAbove 365 days: BoT registration and Debt Registration Number before disbursementForeign Exchange Regulations 2022, reg 25
Shareholder loanCounted as debt for the 7 to 3 test where the lender is a non-resident or associateAs agreed; interest deductibility limited by s.12Income Tax Act s.12(2), (3)

Three ratios follow. Debt to equity is tested against the lender's floor and, where the company is exempt-controlled, against 7 to 3 under section 12. Debt service cover ratio is cash available for debt service divided by scheduled principal and interest in the period. A November 2026 note by Forvis Mazars records lenders targeting around 1.30 times for contracted infrastructure, and no Tanzanian lender page read for this guide prints a minimum. Loan to value on the security is the third, and it decides which of the 25, 10 and 5 percent single-borrower limits in GN 288 the bank is working within. Zatra's note on shareholder loan versus equity and the note on thin capitalisation cover the tax side of the split.

How does TISEZA read the funding plan?

TISEZA reads it for three things. First, that the capital meets the threshold: USD 500,000 or TZS 1,500,000,000 for a foreign or joint venture project, USD 50,000 or TZS 150,000,000 for a Tanzanian-owned one, measured as capital under section 3 of the Act. Second, that the finance is evidenced, because the application list asks for evidence of sufficient finance capital, and the 2026 Chambers chapter by Dentons records that investors must disclose the source of their initial capital, including its source in the home country. Third, that the schedule is credible, because section 17(2)(d) of the Act allows revocation where a project has not started within twelve months, section 17(2)(e) where no progress reports arrive for 24 consecutive months, and section 32(d) requires implementation reports. Section 37(1) adds that a foreign investor may borrow from domestic banks up to a limit set by the Bank of Tanzania in consultation with the Authority, by reference to the foreign capital invested, which is a reason to show the foreign equity line clearly. The NEMBO note on TISEZA incentives and the investor pack and Zatra's note on TISEZA investor registration cover the rest of the file.

Worked example: a TZS 2,400,000,000 agro-processing plant

This worked example follows a sunflower oil plant in Singida promoted by a Tanzanian company with a 30 percent Kenyan shareholder. The split of uses and the contingency percentage are assumptions, stated as such. The lender rules and tax figures are those read on the sources above. Rates are the Bank of Tanzania's reported lending rate of around 15 percent and negotiated rate of around 12 percent from its October and July 2026 monetary policy reports.

Worked example: a TZS 2,400,000,000 agro-processing plant
UsesTZSShareSourcesTZSShare
Land and buildings720,000,00030 percentShareholder equity, paid in840,000,00035 percent
Machinery, freight and installation1,080,000,00045 percentTerm loan, 7 years1,560,000,00065 percent
Working capital to month 4360,000,00015 percent
Contingency, 10 percent of physical cost240,000,00010 percent
Total uses2,400,000,000100 percentTotal sources2,400,000,000100 percent

The tests read as follows. Debt to equity is 1,560 to 840, or 1.86 to 1, under the 7 to 3 ceiling of 2.33 to 1 that applies if the Kenyan holding makes the company exempt-controlled under section 12(3). Equity of 35 percent sits at the top of CRDB's 25 to 35 percent band for an asset loan but below its 40 percent minimum for an agro-processing plant and machinery loan; on that product the promoter would need TZS 960,000,000 of equity. The loan is 65 percent of project cost, inside TADB's 75 percent cap. The capital of TZS 2,400,000,000 exceeds the TZS 1,500,000,000 joint venture threshold for a TISEZA certificate, and the certificate fee for a joint venture is TZS 6,000,000 (TZ-01).

Debt service at 15 percent over seven equal annual instalments uses an annuity factor of 0.2404, giving TZS 375,000,000 a year. Cash available for debt service of TZS 487,500,000 is needed for 1.30 times cover, and TZS 450,000,000 for 1.20 times. At the 12 percent negotiated rate the factor is 0.2191, debt service falls to TZS 341,800,000 and 1.30 times cover needs TZS 444,300,000. Capital allowances support the cash flow: the machinery falls in Class 2 at 25 percent reducing balance under the TRA Glance, and PwC's September 2026 summary adds a 50 percent initial allowance for plant used in manufacturing, a figure the Glance does not print and which belongs in the confirm list. Security costs are small: a charge over TZS 1,560,000,000 is registered at BRELA for TZS 150,000 (F0011) within 42 days, and the loan agreement is stamped at TZS 2,000 (F0267) within 30 days, with the mortgage deed assessed on the Schedule.

Which documents evidence each source?

A credit committee and TISEZA both ask for proof, line by line. Equity is evidenced by a bank statement showing the paid-up capital, the BRELA return of allotment and, for a foreign shareholder, the inward remittance advice that Zatra's note on evidencing a foreign capital injection describes. A term loan is evidenced by the bank's offer letter with its conditions precedent. A foreign loan is evidenced by the signed agreement attested and lodged with the Bank of Tanzania within 14 days under regulation 25, and by the Debt Registration Number. A grant or matching facility is evidenced by the award letter and its disbursement conditions. Retained earnings are evidenced by audited accounts and a board resolution to retain them, with the section 33A deemed distribution modelled. The data room checklist lists where each document sits, and the free SME loan file shows the order a bank reads them in.

What does ZIPA ask for in Zanzibar?

Zanzibar runs its own investment authority and thresholds. The ZIPA investment certificate page read for this guide sets minimum capital at USD 2,500,000 for foreign investors in hotels and real estate and USD 300,000 in other sectors. Citizens need USD 300,000 or USD 100,000. The application fee is USD 200 and certificate fees run in tiers from USD 1,000. The Zanzibar Investment (General) Regulations, 2025 (Legal Notice 59 of 2025) require a business plan and proof of funds at regulation 7(5). Their Second Schedule asks the applicant to split the source of investment finance into foreign equity, local equity, foreign loan and local loan, and to state the implementation period and operative date. That is the sources and uses table in statutory form. Stamp duty on the loan agreement and mortgage in Zanzibar is paid to ZRA under the Stamp Duty Act No. 7 of 2017. Zatra's note on ZIPA incentives covers the certificate.

What to do now

  1. Cost to the first revenue month. List every use with a dated quotation, pro-forma or bill of quantities, in the supplier's currency, and add working capital, interest during construction and a stated contingency.
  2. Classify the capital. Mark which lines are capital under section 3 of the Investment and Special Economic Zones Act, and test the total against the TISEZA or ZIPA threshold that applies to the ownership.
  3. Fix the equity floor. Read the lender's published own-contribution rule for the product, then set equity at or above it and under the 7 to 3 ratio where the company is exempt-controlled.
  4. Evidence every source. Bank statement and allotment for equity, offer letter for the loan, attested agreement and Debt Registration Number for a foreign loan, award letter for a grant.
  5. Run the cover test. Build the debt service schedule at the quoted rate and show cash available for debt service against it for every year of the tenor, with the capital allowance schedule behind it.
  6. Schedule the registrations. Charge at BRELA within 42 days, stamping within 30 days, Bank of Tanzania loan registration within 14 days, and the TISEZA start within twelve months of the certificate.
  7. Reconcile the table to the model. Total uses equal total sources, and both equal the opening balance sheet in the financial model.

Key dates

Key dates
Date or periodWhat happensSource
1 July 2025TISEZA replaces the Tanzania Investment Centre and EPZA under Act No. 6 of 2025Investment and Special Economic Zones Act, 2025
Within 14 days of signing or receiptForeign loan agreement lodged with the Bank of Tanzania; Debt Registration Number before any debt serviceForeign Exchange Regulations 2022, reg 25
Within 30 days of executionLoan agreement and security stampedStamp Duty Act Cap. 189; F0267
Within 42 days of creationCharge registered at BRELACompanies Act Cap. 212; F0011
Within 12 months of the certificateProject must start or the certificate may be revokedAct No. 6 of 2025 s.17(2)(d)
Every reporting periodImplementation and progress reports to TISEZA; revocation after 24 months without themAct No. 6 of 2025 ss.17(2)(e), 32(d)
12 months after year endUndistributed profit deemed 15 percent distributedIncome Tax Act s.33A; F0202
Quarter ending December 2026Central Bank Rate 6.25 percent; lending rates around 15 percentBoT Monetary Policy Report, October 2026

What the NEMBO desk prepares

NEMBO designs the sources and uses table as the first financial page of the business plan and feasibility study, with the evidence index, the debt service schedule and the capital allowance schedule as its annexes, in the lender's and TISEZA's reading order. Bankable plans and feasibility studies are priced by project value and size, not at a fixed price, and the fee is quoted in writing after the brief. Zatra Consultants prepares and checks the content: the cost basis, the lender rule for each product, the thin capitalisation test, the registration calendar and the TISEZA or ZIPA threshold. Every page of the finished work reads free online first, with a Customise for your brand option on the library page.

There are two cost buckets, kept separate on every quotation. Government charges are paid at the official rate to the authority: the TISEZA certificate fee (TZ-01), BRELA charge registration (F0011), stamp duty (F0267) and land charges (F0459, F0462). Bank fees are the bank's own. NEMBO's and Zatra's fees are published on the pricing page. NEMBO does not decide or guarantee any authority's outcome, and the same holds for any bank or tender panel. The process page sets out how a brief becomes a delivered plan.

How Zatra helps

Zatra's financial modelling and forecasting service builds the integrated model behind the table, and its TISEZA investor registration service sequences the certificate with the bank file. The desk is led on investment and market entry by CFE. Joseph Marwa, with the tax tests by CPA Altho Mwangoa. Loan and security documents, the mortgage and any dispute with a lender or the Authority go to an advocate. Brief the desk through the start page, and read the NEMBO notes on feasibility study or business plan and the investment term sheet for the documents on either side of the funding plan.

Next step

Business plan and feasibility study

Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.

Open the desk page

Sources and status

Accurate as at 18 November 2026. The Act, the regulations, the bank pages and the TRA Glance were read on the dates shown. The Investment and Special Economic Zones Regulations 2025 (GN 466 of 2025) were not found online, so the TZS 1,500,000,000 and 150,000,000 thresholds rest on the Zatra fee register. The 50 percent initial allowance for manufacturing plant rests on PwC's summary and is listed to confirm. The split of uses and the contingency in the worked example are assumptions.

Figures to confirm before you act

  • TISEZA thresholds in shillings, TZS 1,500,000,000 and TZS 150,000,000 under regulation 14 of GN 466 of 2025 (TZ-02): the Regulations were not read online; confirm with TISEZA.
  • The 50 percent initial allowance for plant used in manufacturing: PwC lists it; the TRA Glance 2025/2026 does not; confirm against the Third Schedule before modelling it.
  • Section 33A deemed distribution at 15 percent (F0202): the Zatra register reads the Finance Act 2025 at 15 percent while a September 2025 law firm note reports 30 percent; confirm the current text.
  • Whether resident bank debt is excluded from debt in the 7 to 3 test: a 2025 practitioner note reports TRA restricting interest on local loans in practice.
  • Bank of Tanzania limit on domestic borrowing by a foreign investor under section 37(1) of Act No. 6 of 2025: no figure read.
  • Stamp duty on a mortgage deed: Schedule assessment; the agreement rate TZS 2,000 (F0267) is from the register.

This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.

Frequently asked questions

What is a sources and uses of funds statement?

A two-sided table that balances. The uses side lists every cost to the first month of revenue: land, buildings, machinery, vehicles, pre-operating costs, working capital, interest during construction and contingency. The sources side lists the equity, quasi-equity and debt that pay for them, with the provider, amount, currency and status of each. Total uses equal total sources.

How much equity does a Tanzanian bank expect?

It depends on the product. CRDB publishes an equity contribution of not less than 25 to 35 percent on an asset loan and a 40 percent minimum contribution on an agro-processing plant and machinery loan financed on the pro-forma invoice. TADB caps its strategic project loan at 75 percent of project cost, which implies 25 percent from the promoter.

Does TISEZA require a particular funding structure?

No structure, but a threshold and evidence. Capital must reach USD 500,000 for a foreign or joint venture project or USD 50,000 for a Tanzanian-owned one, the application must include evidence of sufficient finance capital, and the project must start within twelve months of the certificate. The foreign equity line also sets the domestic borrowing limit under section 37.

What is the 7 to 3 rule?

Section 12(2) of the Income Tax Act caps deductible interest for an exempt-controlled resident entity at the interest on a debt-to-equity ratio of 7 to 3. An entity is exempt-controlled under section 12(3) where 25 percent or more of its underlying ownership is held by non-residents, exempt persons or their associates. Interest above the cap is not deductible.

Do I have to register a loan from my foreign parent?

Yes, where the tenure exceeds 365 days. Regulation 25 of the Foreign Exchange Regulations 2022 requires the attested agreement to be lodged with the Bank of Tanzania within 14 days, assigns a Debt Registration Number before disbursement and debt service, and charges TZS 1,000,000 a day for late filing. Debt service without the number carries a 10 percent penalty.

What debt service cover ratio do lenders want?

No Tanzanian lender page read for this guide prints a minimum. A November 2026 project finance note records lenders commonly targeting around 1.30 times for contracted infrastructure. Build the schedule at the quoted rate, show cash available for debt service against principal and interest for every year, and ask the bank for its floor in writing.

Should working capital be in the uses column?

Yes, to the month in which operating cash flow turns positive. A plant that is fully built but cannot buy its first three months of raw material is the most common reason a Tanzanian project draws a second, more expensive facility. Derive the line from a 13-week forecast extended to twelve months.

Is the table different for a Zanzibar project?

The form is the same and the Zanzibar Investment (General) Regulations 2025 ask for it in terms: foreign equity, local equity, foreign loan and local loan, with the implementation period. The thresholds differ, at USD 2,500,000 for foreign hotel and real estate projects and USD 300,000 for other sectors, and stamp duty is paid to ZRA.

CPA Altho Mwangoa