- What must a capital expenditure schedule contain?
- Where does each line's evidence come from?
- How is landed cost built from FOB to the factory floor?
- How much contingency, and where do interest and working capital sit?
- Worked example: Singida Sunflower Mills Limited, a TZS 2.4 billion pressing line
- How does a credit committee test the schedule?
- What does TISEZA read in the same schedule?
- Which rules differ between Mainland and Zanzibar?
- What to do now
- Key dates
- What the NEMBO desk prepares
- How Zatra helps
- Sources and status
- Frequently asked questions
What must a capital expenditure schedule show in a Tanzanian feasibility study?
A capital expenditure schedule lists every asset and package of works with quantity, unit cost, source of quote, currency and rate, duty and VAT treatment, landed cost, month of spend and funding source, then adds contingency, capitalised interest and working capital. IAS 16 fixes what cost includes; the EAC CET and TRA fix the import taxes.

What the law says
No Tanzanian statute prescribes the layout of a capital expenditure schedule. The law fixes the cost of each line and names the professionals whose signature carries it. The accounting rule comes first. Under IAS 16, an item of property, plant and equipment is measured at cost. The IFRS Foundation summary says cost is "its purchase price, including import duties and non-refundable purchase taxes", plus "any costs directly attributable to bringing the asset to the location and condition necessary" for it to operate as management intends. Freight, insurance, port charges, installation and commissioning therefore belong in the schedule.
The tax rules decide what those import lines cost. Customs duty follows the East African Community Common External Tariff. The EAC trade regime page gives four bands in force since 1 July 2022: "0% for raw materials and capital goods", 10 and 25 per cent for intermediate goods, and 35 per cent for finished products available in the region. TRA's Taxes and Duties at a Glance 2025/26 adds import VAT at 18 per cent on goods entering Mainland Tanzania and a Railway Development Levy at 2 per cent of customs value. From 1 July 2026 the Customs Processing Fee is set by GN No. 158D of 2026 at 1 per cent of the FOB value of dry cargo. VAT deferment on imported capital goods was due to end on 30 June 2026. According to a Clyde & Co note of 3 July 2026, the Finance Act 2026 abolished that sunset, subject to conditions the Minister may prescribe.
Three registration Acts cover the building lines. The Architects and Quantity Surveyors (Registration) Act Cap. 269 makes it an offence to practise as an architect or to hold oneself out as a quantity surveyor without registration, with a fine of not less than TZS 500,000 or imprisonment. The Contractors Registration Board registers general contractors in seven classes with a value ceiling per class. The Engineers Registration Board keeps the register of engineers under Cap. 63. For the investment file, the TISEZA Certificate of Incentives page asks for a "project business plan" and "evidence of sufficient finance capital available to implement the project" under the Investment and Special Economic Zones Act 2025. Section 15(2) of that Act leaves the procedure to regulations, so the thresholds sit in the verify tier below.
Who should read this
This guide is for the promoter with a quotation folder and a bank appointment, the finance officer who must turn that folder into a project cost, and the adviser who signs the feasibility study. It is written for a Mainland company borrowing from a bank, TADB or a development lender, and registering with TISEZA. Zanzibar projects file with ZIPA under a different Act and pay island taxes, covered below. The schedule feeds the funding plan in Sources and Uses of Funds Tanzania and the cover ratios in Debt Service Coverage Ratio Business Plan Tanzania. It is the page of a business plan or feasibility study that a credit analyst reads with a calculator.
What must a capital expenditure schedule contain?
A capital expenditure schedule is a table, not a paragraph. Each row is one asset or one package of works. Each column answers a question the lender would otherwise ask. The ADB's Cost Estimation in Sovereign Operations note of February 2022 separates base cost from physical and price contingency, and adds interest during construction and taxes and duties as distinct items. A Tanzanian feasibility study follows the same anatomy.
| Column | What it records | Why the reader needs it |
|---|---|---|
| Item and specification | Make, model, capacity, HS heading for imports | Ties the line to a quotation and a tariff row |
| Quantity and unit cost | Units, rate per unit, extended amount | Lets the analyst re-add the total |
| Source of quote | Supplier name, quotation number, date, validity | Shows the price is current and attributable |
| Currency and rate | Original currency, exchange rate used, rate date and source | Separates price risk from currency risk |
| Duty and VAT treatment | CET band, VAT at 18 per cent, deferment or exemption claimed | Prevents a tax surprise at the port |
| Landed cost | FOB plus freight, insurance, levies, clearing and inland transport | Matches the IAS 16 cost of the asset |
| Timing by month | Month of order, shipment, arrival, installation, payment | Drives the drawdown and interest during construction |
| Funding source | Equity, term loan, supplier credit, grant, lease | Reconciles the schedule to sources of funds |
| Contingency | Physical allowance by line or by block, stated as a percentage | Shows the sponsor expects variation and has funded it |
| Capitalised interest | Interest and fees during construction, by month | Part of project cost until commissioning |
| Working capital | First stock, receivables and operating cash to first sale | Closes the gap between commissioning and cash collection |
Two rows are often missing from a first draft: pre-operating cost, meaning design fees, permits, TISEZA facilitation, OSHA registration and product certification, and working capital. The assumptions page of the model should carry the exchange rate, inflation index and contingency rate, so that the schedule and the model never disagree.
Where does each line's evidence come from?
A number without a document behind it is an opinion. Build the evidence file line by line.
Imported plant and equipment
The quotation or pro-forma invoice should state the Incoterm, currency, validity period, lead time, payment terms and HS classification. A pro-forma addressed to the borrowing company, not to a director, is what the bank later attaches to a letter of credit; Pro-Forma Invoice for Imports and Letters of Credit sets out the fields. Where the quotation is in USD and the loan in TZS, record the exchange rate, its date and source. The Bank of Tanzania publishes indicative rates on bot.go.tz; on 23 November 2026 its home page showed USD buying at TZS 2,659.89 and selling at TZS 2,686.49.
Civil works and buildings
Buildings are priced from a bill of quantities prepared by a quantity surveyor. Cap. 269 does not say in terms that a bill must bear a registered signature. It says that an unregistered person may not hold himself out as a quantity surveyor, and the AQRB states that it checks that work is done by registered firms under Cap. 269, Revised Edition 2023. A lender's technical reviewer will ask for the AQRB registration number of the firm that measured the works and for the drawings behind the bill. The contractor should hold a CRB class whose ceiling covers the contract value, and designs should come from an ERB-registered engineer. Land evidence sits beside the bill: a certificate of occupancy or lease, a building permit and, where triggered, a NEMC certificate. Local supplies are quoted VAT inclusive; show the VAT separately, since a registered company recovers it.
How is landed cost built from FOB to the factory floor?
Landed cost is a chain of additions, and later charges are calculated on earlier ones. For Chapter 84 machinery entering Dar es Salaam for a Mainland plant, the chain runs as follows.
- FOB price from the quotation, converted at the stated rate.
- Freight and insurance to the port of entry, from the forwarder's quotation, giving the CIF value used as customs value.
- Import duty at the CET band for the tariff row. Machinery classified as capital goods sits in the nil band. Deemed capital goods such as structural steel, cabling and a generator do not. The Zatra note on capital goods duty exemption explains how a TISEZA certificate relieves part of that duty, and only after TRA's Commissioner General approves it.
- Railway Development Levy at 2 per cent of customs value.
- Customs Processing Fee at 1 per cent of FOB value under GN No. 158D of 2026.
- Import VAT at 18 per cent. The TRA guide names the rate but not the base. The Zatra note on import duty, VAT and excise says the base "often includes duty and other charges" and tells the reader to confirm it. Where VAT deferment on capital goods is approved, the cash moves to a memorandum line.
- Port, clearing and inland transport from the agent's and transporter's quotations.
- Installation, commissioning and training, often a separate supplier quotation in foreign currency.
Two items are easy to omit. The Industrial Development Levy, extended by the Finance Act 2026 to steel structures and trailers according to an EY note of 17 July 2026, falls on a shed imported as a kit. Excise falls on a site vehicle. Zatra's landed cost calculator walks the same chain.
How much contingency, and where do interest and working capital sit?
Contingency is a priced statement that quantities and prices will move between quotation and invoice. The ADB guidance note of February 2022 says that "physical contingencies normally range between 5% and 10% of the base cost", and that price contingencies "are calculated as a percentage of the sum of the base cost and physical contingencies" using forecast inflation. The same note treats interest during construction as project cost until the facilities are ready. No Tanzanian bank page read for this guide publishes a required contingency rate. The test is whether the rate is stated, applied consistently and funded.
A Tanzanian schedule should show three allowances. A physical contingency of 5 to 10 per cent on equipment and works, higher on earthworks and remote sites. A price contingency on the local currency portion where construction runs beyond a year. An exchange rate movement on the foreign currency portion, shown as a sensitivity rather than a cost, as the sensitivity analysis guide describes. Interest during construction is calculated from the drawdown schedule, month by month, at the rate the bank has quoted in writing, and capitalised until commissioning. Working capital is sized from the operating model: first raw material, first payroll, utilities and the receivable days of the first customers, less supplier credit. It is project cost for the funding plan.
Worked example: Singida Sunflower Mills Limited, a TZS 2.4 billion pressing line
Singida Sunflower Mills Limited is an illustrative citizen-owned company planning a 60 tonne per day sunflower pressing and refining line on a plot it holds under a certificate of occupancy. The line is quoted FOB Mumbai in USD. The exchange rate used is USD 1 to TZS 2,680, an illustrative round rate close to the Bank of Tanzania selling rate of 23 November 2026. All figures are illustrative; the tax lines follow the published rates named above.
| Line | Basis | Evidence | TZS |
|---|---|---|---|
| Pressing and refining line, FOB Mumbai | USD 310,000 at 2,680 | Pro-forma invoice, valid 90 days, HS 8479 | 830,800,000 |
| Ocean freight and marine insurance to Dar es Salaam | USD 18,600 at 2,680 | Forwarder quotation | 49,848,000 |
| Import duty | CET nil band, capital goods | Tariff classification letter from clearing agent | 0 |
| Customs Processing Fee | 1 per cent of FOB | GN No. 158D of 2026 | 8,308,000 |
| Railway Development Levy | 2 per cent of CIF | TRA guide 2025/26 | 17,612,960 |
| Port, clearing and transport to Singida | Quotation | Clearing agent and transporter quotations | 38,000,000 |
| Installation, commissioning and training | USD 24,000 at 2,680 | Supplier service quotation | 64,320,000 |
| Factory shed, tank bases and drainage | Bill of quantities | BoQ by registered QS, drawings, building permit | 420,000,000 |
| Power connection and 315 kVA transformer | Quotation | TANESCO quotation, electrical contractor quotation | 95,000,000 |
| Steel storage tanks and seed silos, local fabrication | Quotation, VAT excluded | Fabricator quotation, ERB-registered design | 130,000,000 |
| Design, permits and professional fees | Fee letters | Architect, QS, engineer, NEMC and permit receipts | 62,000,000 |
| Pre-operating costs | Estimate | TISEZA facilitation, OSHA, product certification, recruitment | 25,000,000 |
| Base cost | Sum of lines above | 1,740,888,960 | |
| Physical contingency | 7.5 per cent of base cost | Stated in assumptions | 130,566,672 |
| Import VAT on the line | 18 per cent of CIF, duty nil | Deferment not yet approved | 158,516,640 |
| Interest during construction | Drawdown schedule, nine months | Bank term sheet, rate illustrative | 84,000,000 |
| Working capital to first sale | Three months seed, payroll, utilities | Operating model | 310,000,000 |
| Total project cost | 2,423,972,272 |
The CIF value is TZS 880,648,000; the levy is 2 per cent of it and the processing fee is 1 per cent of the FOB figure. The VAT line is 18 per cent of CIF because duty is nil. Interest during construction assumes TZS 1,400,000,000 drawn evenly over nine months, an average balance of about TZS 700,000,000, at an illustrative 16 per cent. The sponsor offers equity of TZS 650,000,000 in cash and the plot, and asks for a loan of TZS 1,775,000,000, which is 73.2 per cent of project cost.
Now the missing line. The first draft left out import VAT because the promoter expected deferment. The draft total was TZS 2,265,455,632. Against sources of TZS 2,425,000,000 the draft showed a surplus of about TZS 159,500,000, and the promoter cut equity to TZS 490,000,000. The credit analyst restored the VAT line, since no deferment approval was in the file. Project cost rose to TZS 2,423,972,272 and sources fell short by TZS 158,972,272. The gap fell on equity, which returned to about TZS 650,000,000: one missing line moved the equity requirement by a third. Had the bank been asked to fund the gap, the loan would have reached 79.8 per cent of project cost. That is above the 75 per cent of project cost that TADB's strategic projects page states as its term loan ceiling. It also breaches the equity contribution of not less than 25 to 35 per cent that CRDB's investment financing page states for an asset loan.
How does a credit committee test the schedule?
A credit committee does not rebuild the schedule; it samples it. The tests below are the ones Zatra's desk sees most often in bank queries. None is published as a rule.
| Test | What the analyst looks for | What fails |
|---|---|---|
| Quotation age | Quotation date and validity against the expected drawdown date | A quotation past its validity, or older than about 90 days with no refresh |
| Currency | Rate, date and source stated; sensitivity shown | USD lines converted at a rate with no date |
| Duty and VAT | Each import line shows band, levy, fee and VAT treatment | Nil tax on a deemed capital good; VAT omitted without approval |
| Contingency | Stated rate, applied to base cost, funded in sources | No contingency, or contingency used to fund a known item |
| Civil works | BoQ from a registered QS, drawings, permit, CRB class | A lump sum from an unregistered builder |
| Sources match uses | Total project cost equals equity plus debt plus other sources | A gap, or a surplus with no explanation |
| Equity evidence | Bank statements, land valuation, paid invoices for sunk cost | Equity described but not evidenced |
The committee also reads the schedule against the fixed asset register the company will keep, because the loan security will be a charge over those assets. Each line should be capable of becoming a register entry with a tag, a location and a matching cost. The SME loan file checklist lists the documents a Tanzanian bank asks for around the schedule.
What does TISEZA read in the same schedule?
The bank asks whether the project can repay. TISEZA asks whether the project meets the threshold and which lines qualify for relief. The Certificate of Incentives page states a minimum investment value of USD 50,000 for a project wholly owned by Tanzanian citizens and USD 500,000 for a wholly foreign-owned project or joint venture. The Zatra note of 15 September 2026 cites regulation 14 of GN No. 466 of 2025 for TZS 150,000,000 and TZS 1,500,000,000. The readings differ and the regulations were not opened for this guide, so confirm the threshold with TISEZA before filing. Section 21 of the 2025 Act sets strategic investor status at the TZS equivalent of USD 20,000,000 for a domestic investor and USD 50,000,000 for a foreign investor.
For relief, TISEZA's certificate carries an annexed equipment schedule: item, HS heading, quantity, value and source. A line missing from the annex cannot be relieved at the port, and the Zatra note says the certificate alone releases nothing until TRA's Commissioner General approves the relief. The TISEZA investor pack guide describes the file, and Zatra's page on TISEZA investor registration covers the portal. The facilitation fee is paid on a TISEZA control number at the published rate.
After commissioning, the schedule becomes the tax base. Under the Income Tax Act Cap. 332 Third Schedule, as summarised in TRA's 2025/26 guide, manufacturing plant falls in Class 2 at 25 per cent reducing balance and buildings in Class 6 at 5 per cent straight line. The Zatra note of 10 October 2026 on capital allowances describes a 50 per cent initial allowance on plant fixed in a factory, taken in two portions since the Finance Act 2024. The accountant computes the allowance; the schedule should tag each line with its class.
Which rules differ between Mainland and Zanzibar?
A Zanzibar project files with the Zanzibar Investment Promotion Authority, not TISEZA. The Zanzibar Investment (General) Regulations 2025, Legal Notice No. 59 of 2025 made under the Zanzibar Investment Act No. 10 of 2023, list in regulation 7(5) a business plan and a "statement of proof for fund" among the application documents. The application form asks for the intended capital investment in USD. Zanzibar VAT is administered by the Zanzibar Revenue Authority; the Zatra note of 15 September 2026 gives the island rate as 15 per cent, and the Zanzibar VAT Act was not read for this guide. Building permits come from Zanzibar's own authorities, and professional registration for island works should be checked there.
| Point | Mainland | Zanzibar |
|---|---|---|
| Investment authority | TISEZA, Act No. 6 of 2025 | ZIPA, Zanzibar Investment Act No. 10 of 2023 |
| Application evidence | Business plan, evidence of finance, project location, board resolution | Business plan, statement of proof of funds, incorporation and identity documents |
| Import VAT | 18 per cent, TRA, deferment on capital goods continues under the Finance Act 2026 | ZRA, island rate reported as 15 per cent; instrument not read |
| Building permit | Local government authority, NEMC where triggered | Zanzibar authorities; confirm the issuing body |
| Relief route | TISEZA certificate, TRA approval | ZIPA certificate; see ZIPA incentives |
What to do now
- List every asset the project needs to reach first sale, including pre-operating cost and working capital.
- Collect quotations addressed to the company, dated, with validity, Incoterm, currency and HS heading.
- Commission the bill of quantities from an AQRB-registered firm working from drawings by a registered architect and engineer, and record the numbers.
- Build the landed cost line by line: FOB, freight and insurance, duty band, levy, processing fee, VAT treatment, clearing, transport and installation.
- Fix the exchange rate and its date from the Bank of Tanzania, and show a sensitivity on the foreign currency portion.
- Add contingency, interest and working capital as separate lines, with the rate and the basis stated, and carry them into the sources of funds.
- Reconcile sources to uses so that equity plus debt equals total project cost, with equity evidenced by statements and valuations.
- Tag each line with its funding source, month of spend, TISEZA annex status and capital allowance class.
- Refresh before submission: replace any quotation older than 90 days at the expected drawdown date, and re-run the totals.
Key dates
- 30 June 2026: the planned end of VAT deferment on imported capital goods; the Finance Act 2026 removed that sunset.
- 1 July 2026: the Customs Processing Fee Regulations 2026 came into operation at 1 per cent of FOB for dry cargo.
- 1 July 2027: the next Finance Act takes effect; every rate in the schedule should be re-checked on that date.
- Quotation validity: a schedule is only as current as its oldest quotation.
What the NEMBO desk prepares
NEMBO designs and delivers the capital expenditure schedule as part of a business plan or feasibility study. The set holds the schedule, the landed cost workings, the drawdown and interest table, the reconciled sources and uses page, an evidence index that maps every line to its document, and the TISEZA equipment annex. The market study is built on the same assumptions page, and the investor documents desk carries the schedule into an information memorandum where the file goes to investors. Zatra Consultants prepares and checks the content on the details the Client shares, including the quotations, drawings and registrations supplied. NEMBO does not decide or guarantee any authority's outcome. Two cost buckets apply. Government, bank or regulator charges, such as the TISEZA facilitation fee, permit fees, customs duty and bank fees, are paid at the official rate on the authority's control number. They are separate from NEMBO's and Zatra's fees, published on the packages page and quoted in writing. The order runs as described on the process page, and a project starts when the Client shares the details.
How Zatra helps
Zatra Consultants Limited prepares the financial content of the schedule through its business plans and feasibility studies service and its financial modelling and forecasting service. The TISEZA investor registration service prepares the application and the equipment annex, and Zatra's note on evidencing source of funds covers the equity side. The tax computation, the capital allowance claim and any audited figures the bank asks for go to the accountant, CPA Altho Mwangoa. A dispute over a tariff classification, a contractor's claim, a permit refusal, a notarised document or a legal opinion on a land title goes to an advocate. Feasibility Study Market Sizing Tanzania covers the demand side of the same study.
Feasibility study capital expenditure schedule and evidence index
Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.
Open the desk pageSources and status
Accurate as at 24 November 2026. Read in full on 24 November 2026: the TISEZA Certificate of Incentives page, GN No. 158D of 2026, the EAC trade regime page, the IAS 16 summary and the AQRB, CRB, ERB, CRDB and TADB pages. Read in part: the Investment and Special Economic Zones Act 2025, Cap. 269, TRA's 2025/26 guide, the ADB note and the Zanzibar regulations. VAT deferment, the import VAT base, the initial allowance and the Zanzibar VAT rate rest on Clyde & Co, EY and Zatra notes.
- 1TISEZA, Certificate of IncentivesTISEZA, page read 24 November 2026. Accessed 24 November 2026.
- 2Investment and Special Economic Zones Act, 2025TISEZA, English text published through GN No. 4 of 2026. Accessed 24 November 2026.
- 3Architects and Quantity Surveyors (Registration) Act, Cap. 269Ministry of Lands PDF, read 24 November 2026. Accessed 24 November 2026.
- 4IAS 16 Property, Plant and EquipmentIFRS Foundation, revised December 2003. Accessed 24 November 2026.
- 5Taxes and Duties at a Glance 2025/2026Tanzania Revenue Authority, 2025. Accessed 24 November 2026.
- 6Customs Processing Fee Regulations, 2026, GN No. 158DTanzania Revenue Authority, 30 June 2026. Accessed 24 November 2026.
- 7EAC Trade Regime: Common External TariffEast African Community, page read 24 November 2026. Accessed 24 November 2026.
- 8Cost Estimation in Sovereign OperationsAsian Development Bank, February 2022. Accessed 24 November 2026.
- 9Tanzania Tax Update: Finance Act 2026 HighlightsClyde & Co, 3 July 2026. Accessed 24 November 2026.
- 10Zanzibar Investment (General) Regulations, 2025ZIPA, Legal Notice No. 59 of 2025. Accessed 24 November 2026.
Figures to confirm before you act
- TISEZA minimum investment value: USD 50,000 and USD 500,000 on the TISEZA page; TZS 150,000,000 and TZS 1,500,000,000 in a Zatra note citing GN No. 466 of 2025. Confirm with TISEZA.
- Import VAT base and deferment conditions on capital goods after the Finance Act 2026: confirm with TRA or the accountant.
- Customs Processing Fee at 1 per cent of FOB and Railway Development Levy at 2 per cent: check TRA's schedules for the goods and year of import.
- Capital allowance classes and the 50 per cent initial allowance: confirm against the Third Schedule to Cap. 332 with the accountant.
- Zanzibar VAT at 15 per cent and the island permit route: confirm with ZRA and ZIPA.
- Bank equity contribution and loan ceilings: confirm with the lender's current term sheet.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
How old can a quotation be before a bank rejects it?
No Tanzanian bank page read for this guide sets a limit. Analysts read the validity date on the quotation against the expected drawdown date. A quotation past its validity, or older than about 90 days with no written refresh, is normally sent back for renewal.
Does the schedule show prices with or without VAT?
Both. Record each line net of VAT, then show the VAT in its own column with its treatment: deferred, exempt, recoverable or not recoverable. The net figure is what the auditor capitalises; the VAT column is what the funding plan must finance.
Who can prepare the bill of quantities?
A quantity surveyor or firm registered with the Architects and Quantity Surveyors Registration Board, working from drawings by a registered architect and engineer. Cap. 269 makes it an offence to hold oneself out as a quantity surveyor without registration.
Is working capital part of project cost?
For the funding plan, yes. The lender wants to see that the plant can buy its first raw material, pay its first payroll and carry its first receivables before the first collection. The auditor later classifies the amount as current assets.
Can interest during construction be added to the loan?
Many term loans allow interest during the grace period to be capitalised, added to principal and repaid over the tenor. Whether a bank allows it, and at what rate, is a matter for its written term sheet. Show the amount month by month.
What happens if the exchange rate moves after the schedule is signed?
The foreign currency lines change in TZS while the loan does not. State the rate and date used and show the funding gap at a weaker shilling in the sensitivity analysis. Most lenders expect the sponsor to carry that gap from equity.
Should the schedule include land the company already owns?
Yes, as a line funded by equity in kind, at a valuation by a registered valuer, with the certificate of occupancy attached. The bank reads it as sponsor contribution and as security; TISEZA reads it as evidence of project location.