On this page
- What the law says
- Who should read this
- How does a bidder request a tender clarification?
- What do the pre-tender meeting and its minutes count for?
- How does the procuring entity issue an addendum, and what can it change?
- How is an addendum acknowledged, and what if it is not?
- What may the evaluation committee ask after submission?
- Common faults, and the controls behind the record
- Worked example: Arusha Office Systems Limited, December 2026
- Mainland and Zanzibar: which rules differ?
- What to do now
- Key dates
- What the NEMBO desk prepares
- How Zatra helps
- Sources and status
- Frequently asked questions
How does a bidder request a tender clarification in Tanzania?
A bidder requests a tender clarification in writing through NeST, inside the window the Instructions to Tenderers set, which is at least three days before the deadline under regulation 12(1) of the Public Procurement Regulations, 2024 and seven days in PPRA's standard goods document. The entity replies to all tenderers without naming the asker, and any change is issued as a binding addendum that the Form of Tender acknowledges.

What the law says
A tender clarification is a written question a bidder puts to a procuring entity about the tender document, and the written answer the entity sends to every bidder holding that document. An addendum is the entity's formal change to the document before the deadline. On the Mainland both sit in the Public Procurement Act, 2023 (Act No. 10 of 2023) and the Public Procurement Regulations, 2024, published in English as GN No. 261 of 2025. PPRA's notice of 12 June 2024 states that the Act came into force on 17 June 2024 under GN No. 455 of 2024; regulation 1 gives the Regulations a commencement date of 1 July 2024.
Regulation 10(1) requires communication between tenderers and procuring entities to be in writing through the electronic public procurement system, which in practice is NeST. Regulation 12, headed "Clarification and modifications of tender documents", does four things. Sub-regulation (1) lets a tenderer request clarification at least three days before the deadline in competitive methods, and two days in non-competitive methods. Sub-regulation (2) requires a written reply within two working days to every tenderer that received the documents, without identifying who asked. Sub-regulations (3) and (4) let the entity modify the documents by addendum at any time before the deadline and make the addendum binding on every tenderer. Sub-regulation (5) requires prompt notice of any extension. Regulation 14(1)(l) obliges the entity to keep a summary of every clarification request, response and modification in its record of proceedings.
In the Act, section 73 requires procurement to run through the electronic system and section 84 requires tender documents to be issued immediately after first publication of the notice. Section 88(3) keeps the examination, clarification and evaluation of tenders confidential until the intention to award is notified. Section 71 requires a record of proceedings, kept for at least five years after contract completion as read in PPRA's copy.
The operating detail is in the Instructions to Tenderers (ITT) and Tender Data Sheet (TDS) of the tender document. In PPRA's Standard Tendering Document for General Goods, February 2022, ITT 8 covers clarification, ITT 9 addenda, ITT 27 clarification during evaluation and ITT 28 responsiveness. That edition names TANePS; live 2025 documents name NeST and renumber some clauses. PPRA's Guidelines for the Use of NeST, 2025, approved on 29 July 2025, describe how clarifications and modifications move through the system. The Regulations also list regulation 198 (pre-tender meeting) and regulation 214 (request for clarification of tender); this post could not read either text, so their content below comes from the standard documents. The Chanzo's report of 12 September 2023 and a review in Cogent Business and Management, December 2024 give the reform context.
Who should read this
This guide is for the managing director who signs the Form of Tender, the bid manager, the company secretary and the consultant who prepares bids for clients. Read it if a tender document is unclear, if an addendum has landed ten days before the deadline, or if an evaluation committee has written asking for a confirmation. Skip it if the question is NeST registration, covered by the NeST registration post, or the complaint route after an award notice, covered by the PPAA appeal file post.
How does a bidder request a tender clarification?
The request goes through NeST, in writing, inside the window the tender document sets. Regulation 12(1) fixes the floor at three days before the deadline for competitive methods. The ITT usually sets a longer window: ITT 8.1 of the 2022 goods document requires the request not later than seven days before the deadline for open methods and three days for others. A Tanzania Revenue Authority tender document of 21 March 2025, read on a third-party mirror, names NeST and keeps the seven-day rule. The bidder applies the longer period and files early; a late request has no right to an answer.
The 2025 NeST guidelines say the reply is due within two working days and goes to all tenderers through the system. It describes the question without naming the bidder (ITT 8.2; regulation 12(2)), so every competitor sees the same question and answer.
What the clarification request letter contains
A signed letter on the company letterhead, uploaded in NeST, is the better record. It carries:
- The tender number and title exactly as published, and the date of the invitation.
- The clause, page or line being queried, cited exactly.
- One question per numbered paragraph, phrased so it can be answered yes, no or with a figure.
- A request that the answer go to all tenderers and, where it changes the document, be issued as an addendum.
It never contains the bidder's intended price, a complaint that the specification favours a competitor, or a request for a meeting; ITT 27.1 says an unsolicited clarification from a tenderer will not be considered.
What do the pre-tender meeting and its minutes count for?
Goods tenders rarely hold one; works and installation tenders often do. PPRA's Standard Tendering Document for Small Works, February 2022 sets the model in ITT 6. The entity may hold a site visit and pre-tender meeting to explain the project and answer questions (ITT 6.3); non-attendance is not a ground for disqualification (ITT 6.4). Minutes, with the questions and responses but no sources, go to all participating tenderers within three working days (ITT 6.6).
The sentence that matters most is the last one in ITT 6.6: minutes do not amend the document, and any change is made only by addendum under ITT 9. A bidder who prices on a verbal answer that never becomes an addendum has priced on nothing. The TRA document's TDS records no site visit and no pre-tender meeting, the usual goods position.
How does the procuring entity issue an addendum, and what can it change?
Regulation 12(3) allows the entity to modify the tender documents "by issuing an addendum" at any time before the deadline, for any reason, on its own initiative or following a request. Regulation 64(5) requires the modification to be approved by the accounting officer or the tender board. The addendum goes through NeST to every tenderer that received the documents, becomes part of the tendering documents including any notice of extension (ITT 9.2), and binds every tenderer (regulation 12(4)). Three changes move a bid:
- Specification. A performance figure, a standard, a delivery point or a warranty period. The bidder re-prices the affected lines against the new wording.
- Deadline. ITT 22.2 lets the entity extend the deadline, in exceptional circumstances and before it expires, so that tenderers have reasonable time to take the addendum into account (ITT 9.3). The TRA document's TDS caps its own extension at 14 days, a figure for that tender, not the law.
- Price schedule. A changed quantity, a split lot, an added line or a changed delivery term. The bidder rebuilds the schedule from the addendum, because the committee checks it against the schedule as amended.
How is an addendum acknowledged, and what if it is not?
PPRA's standard Form of Tender opens with an acknowledgement. In the Disposal of Public Assets document, February 2022, the form begins "Having examined the Tendering Documents including Addenda Nos." followed by a blank, continues "the receipt of which is hereby duly acknowledged", and offers "in conformity with the said Tendering Documents". This post could not read the goods form, so confirm the wording in the document issued; in NeST the form is completed in the system. The acknowledgement tells the committee which version of the document the price answers.
If the form lists no addenda when one was issued, the committee applies ITT 28. Responsiveness rests on the contents of the tender itself (ITT 28.1). A substantially responsive tender conforms to all terms, conditions and specifications without material deviation, omission or reservation; a material deviation would substantially affect the scope, quality or performance of the goods (ITT 28.2). The entity may waive a minor informality (ITT 28.4) and may ask for information to cure a non-material gap, but not on price (ITT 28.5). A tender that is not substantially responsive is rejected and cannot be made responsive later (ITT 28.7).
So the test is what the bid shows. A bid priced on the old quantity and specification has material deviations and is likely out; a bid priced to the addendum with the number left blank has a clerical omission the committee may waive or query. The bidder removes the risk by listing every addendum number in the form and marking the revised lines "as per Addendum No. 1".
What may the evaluation committee ask after submission?
After opening, the committee may write to a bidder for a clarification that assists evaluation. ITT 27.2 of the 2022 goods document, repeated as ITT 29.2 in the TRA document, states the limit: "no change in the prices or substance of the Tender shall be sought, offered, or permitted". The single exception is confirming the correction of arithmetic errors. Regulation 214, "Request for clarification of tender", was not read; the rule above comes from the standard documents.
The committee may ask which page carries the manufacturer's authorisation, or whether "60 days" means calendar days. It may not ask, and the bidder may not offer, a lower price, a longer warranty, a substitute product, or a document created after the deadline.
ITT 30 sets the arithmetic order: unit price prevails over an inconsistent total unless the decimal point is obviously misplaced, subtotals prevail over the total, and words prevail over figures. The corrected amount binds the bidder once it concurs (ITT 30.2); a refusal means rejection. The price schedule post works through the arithmetic. The reply answers only what was asked, cites the page in the submitted bid, and is signed by the person named in the power of attorney for tender signing.
Common faults, and the controls behind the record
The record is the bidder's defence in an evaluation query and in a complaint. Regulation 14(1)(l) tells the entity what it keeps; the bidder keeps the mirror image. The 2025 NeST guidelines say the system keeps records for five to seven years after contract completion. The record retention post gives the company-side periods.
| Fault | What it costs | Fix and control |
|---|---|---|
| Request filed after the ITT window but before the regulation 12 floor. | No reply; the bid is priced on an assumption. | Bid manager diarises both dates; the earlier governs. |
| Addendum downloaded but the old price schedule reused. | Material deviation; rejection under ITT 28.7. | Rebuild the schedule from the addendum; second person checks. |
| Form of Tender lists no addenda. | A query at best, a responsiveness finding at worst. | Signatory ticks each addendum number against the NeST notice log. |
| Reply to the committee adds a better offer. | Breach of ITT 27.2; the bid may be rejected. | Reply answers the question only; the managing director signs. |
Who does what. The bid manager drafts the request and tracks the clock. The company secretary reviews the wording and keeps the file. The finance manager re-prices after an addendum and concurs with arithmetic corrections. The managing director, or the attorney under the power of attorney, signs the form and every reply. The free tender evidence index gives the file structure.
Worked example: Arusha Office Systems Limited, December 2026
Arusha Office Systems Limited is a fictional supplier; all figures are illustrative. A regional authority publishes on NeST, on 1 December 2026, an open national tender for computers, printers and chairs, deadline 29 December 2026 at 10:00, with a seven-day clarification window. The bid manager finds that the printer line names 30 pages per minute while the specification annex names 40, and that the chair quantity differs between two schedules.
| Date | Event | Rule and record |
|---|---|---|
| 1 December 2026 | Tender published on NeST; documents downloaded. | Act s.84; document saved to the tender file. |
| 15 December 2026 | Clarification request uploaded: two numbered questions. | Inside the 7-day window (last day 22 December); signed letter kept. |
| 17 December 2026 | Entity publishes its reply to all tenderers, source not named. | Regulation 12(2); ITT 8.2. |
| 18 December 2026 | Addendum No. 1: printers at 40 pages per minute, chairs 55 units, deadline moved to 5 January 2027 at 10:00. | Regulation 12(3) to (5); ITT 9 and 22.2. |
| 22 December 2026 | Finance manager re-prices lines 2 and 3; price schedule version 2. | Rebuilt from the addendum; version log updated. |
| 4 January 2027 | Bid submitted in NeST; Form of Tender lists "Addenda Nos. 1". | Acknowledgement in the form; addendum attached. |
| 5 January 2027 | Deadline and opening; opening report generated by NeST. | ITT 22 and 23; report saved. |
| 12 January 2027 | Committee asks whether "36 months" in the warranty line runs from delivery. | ITT 27; no change in price or substance. |
| 14 January 2027 | Reply uploaded, citing page 41 of the bid; signed by the managing director. | Copy kept with the request. |
The company labelled the second price schedule "as per Addendum No. 1" and submitted only that version. Figures exclude VAT.
| Line | Before Addendum No. 1 | After Addendum No. 1 | Change |
|---|---|---|---|
| 1. Desktop computers, 20 units at TZS 1,850,000 | TZS 37,000,000 | TZS 37,000,000 | None |
| 2. Multifunction printers, 10 units | 30 ppm at TZS 2,400,000: TZS 24,000,000 | 40 ppm at TZS 3,100,000: TZS 31,000,000 | +TZS 7,000,000 |
| 3. Office chairs at TZS 285,000 | 40 units: TZS 11,400,000 | 55 units: TZS 15,675,000 | +TZS 4,275,000 |
| Total excluding VAT | TZS 72,400,000 | TZS 83,675,000 | +TZS 11,275,000 |
Had the company submitted version 1, the committee would have found two material deviations under ITT 28.2 and a rejection under ITT 28.7 that no later letter could cure.
Mainland and Zanzibar: which rules differ?
Everything above is Mainland law. Zanzibar runs its own system: until 2025 the Public Procurement and Disposal of Public Assets Act, No. 11 of 2016, with its own authority. The Zanzibar House of Representatives published a Bill Supplement of 5 November 2024 for a new Public Procurement Act, and its list of Acts for 2025 shows the Public Procurement Act, No. 2 of 2025, described as repealing the 2016 Act. In the Bill as read, the regulator is the Zanzibar Public Procurement Regulatory Authority and section 51 requires use of its electronic system. Section 62 lets an entity modify bid documents before the deadline, on its own initiative or after a bidder's request, and extend the deadline. Section 69 lets it seek clarification from bidders during evaluation.
This post did not read the Act as passed, any Zanzibar regulations or Zanzibar's standard bidding documents, so the clarification windows, reply periods and addendum procedure there are unconfirmed. A bidder in a Zanzibar tender reads the document issued and takes any dispute to an advocate practising there.
What to do now
- Diarise two dates: record the NeST deadline and the ITT clarification window, and set the last day for questions.
- Read for conflicts: read the schedule of requirements, the specification and the price schedule against each other and list every inconsistency.
- Draft the request letter: one numbered question per point, clause cited, no price or product named; company secretary reviews; upload through NeST and keep the signed copy.
- Attend the pre-tender meeting if one is held: submit questions in advance, keep the minutes, and price nothing on a verbal answer that is not in an addendum.
- Process every addendum the day it lands: log the number and date, mark the changed clauses, rebuild the price schedule as a new version, and re-check the deadline and the window.
- Acknowledge in the form: list every addendum number in the Form of Tender, attach the addenda, label the revised schedule, and have the signatory under the power of attorney sign.
- Answer the committee narrowly: reply through NeST within the time stated, cite the page of the submitted bid, confirm arithmetic corrections after the finance manager checks them, and offer nothing new.
- Close the file: index the invitation, requests, replies, addenda, both schedule versions, the bid, the opening report and every committee exchange, and keep it to the retention period.
Key dates
The clock runs from the deadline shown in NeST, fixed by the data centre server time under the 2025 guidelines. Regulation 12(1): request at least three days before the deadline in competitive methods, two in non-competitive methods. ITT 8.1 in the 2022 goods document and the 2025 TRA document: seven days for open methods, three for others. Regulation 12(2): reply within two working days; ITT 8.2 of the 2022 document says three, so read the figure in the document issued. Extension: before expiry under ITT 22.2, with prompt notice under regulation 12(5). Records: section 71 of the Act, at least five years after completion as read; the NeST guidelines say five to seven. December public holidays shorten the working-day count.
What the NEMBO desk prepares
The NEMBO tender documents desk prepares the clarification request letter, the addendum log and acknowledgement sheet, the versioned price schedule, the reply template for a committee request, and the indexed tender file. Zatra Consultants checks every clause reference against the document issued and the current Regulations before release, with Joseph Marwa as the reviewer for the tendering beat. The client shares the details of the tender, and the desk returns the drafts on the published process.
Two cost buckets apply: government, bank or regulator charges are paid at the official rate and are separate from NEMBO's and Zatra's fees, which are published on the packages page and quoted in writing. NEMBO does not decide or guarantee any authority's outcome.
How Zatra helps
Zatra Consultants' tender and procurement advisory reviews the tender document before the window closes, drafts the questions and prepares the evaluation-stage replies. Its note on registering as a government supplier covers the NeST side, and its business licensing service keeps the eligibility documents current. The eligibility documents post and the evaluation criteria post set out what the committee reads next. CPA Altho Mwangoa signs any tax computation or audited figure a bid relies on. A contested rejection, a complaint to the accounting officer, an appeal to the Public Procurement Appeals Authority, a formal legal opinion on a Zanzibar tender, or anything before a court or tribunal goes to an advocate.
Tender clarification and addendum file
Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.
Open the desk pageSources and status
Accurate as at 26 November 2026. Regulations 1 to 69 of the Public Procurement Regulations, 2024 (GN No. 261 of 2025) and the Act to section 98 were read in the published PDFs; the text of regulations 198, 208, 214 and 286 was not read and is cited by heading only. The February 2022 standard documents were read to the responsiveness and arithmetic clauses; the Form of Tender wording comes from the disposal document. Zanzibar rests on the November 2024 Bill and the House's 2025 Acts list, not the Act as passed.
- 1The Public Procurement Act, 2023 (Act No. 10 of 2023)PPRA, assented 29 September 2023. Accessed 26 November 2026.
- 2The Public Procurement Regulations, 2024 (GN No. 261 of 2025, English version)Ministry of Finance, GN published 25 April 2025. Accessed 26 November 2026.
- 3New Public Procurement Law to take effect on June 17, 2024PPRA, 12 June 2024. Accessed 26 November 2026.
- 4Standard Tendering Documents for Procurement of General GoodsPPRA, February 2022. Accessed 26 November 2026.
- 5Standard Tendering Documents for Procurement of Small WorksPPRA, February 2022. Accessed 26 November 2026.
- 6Standard Tendering Document for Disposal of Public Assets by TenderPPRA, February 2022. Accessed 26 November 2026.
- 7Guidelines for the Use of the National Electronic Procurement System of Tanzania in Public Procurement and Supply Management, 2025PPRA, approved 29 July 2025. Accessed 26 November 2026.
- 8Bill Supplement: The Public Procurement Act, 2024 (Zanzibar)Zanzibar House of Representatives, 5 November 2024. Accessed 26 November 2026.
- 9Tanzania's New Public Procurement Act: Reforms or Business as Usual?The Chanzo, 12 September 2023. Accessed 26 November 2026.
- 10Public procurement trajectories in Tanzania: a review of reforms, practices, and complianceCogent Business and Management, December 2024. Accessed 26 November 2026.
Figures to confirm before you act
- Regulation 12(1) windows (three days competitive, two days non-competitive) and regulation 12(2) reply period (two working days): read in GN No. 261 of 2025; confirm against the ITT of the tender issued, which may set a longer window.
- Regulations 198 (pre-tender meeting), 208 (influence by tenderer), 214 (request for clarification of tender) and 286 (no change of price or substance): headings read in the arrangement, text not read; confirm before citing.
- ITT clause numbers (8, 9, 22, 27, 28, 30) are from PPRA's February 2022 goods document under TANePS; live 2025 documents renumber them (TRA document: ITT 9, 10, 24, 29); read the clause by heading.
- Form of Tender addenda acknowledgement wording was read in the disposal document; confirm the goods form in the document issued.
- Act section 71 retention (at least five years after completion) as read in PPRA's PDF against the NeST guidelines' five to seven years.
- Zanzibar: Public Procurement Act, No. 2 of 2025 listed as repealing Act No. 11 of 2016; the Act as passed, its regulations and standard bidding documents were not read.
- Worked example figures (TZS 1,850,000; TZS 2,400,000; TZS 3,100,000; TZS 285,000; totals TZS 72,400,000 and TZS 83,675,000) and all example dates are illustrative.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
Can a bidder ask for a clarification by email or phone?
No. Regulation 10(1) of the Public Procurement Regulations, 2024 requires communication between tenderers and procuring entities to be in writing through the electronic procurement system. An email to an officer leaves no record the committee must consider, and a phone call leaves none. Upload the letter in NeST and keep the system receipt.
Does the procuring entity have to answer every clarification request?
A request lodged inside the window set by the tender document earns a written reply to all tenderers under regulation 12(2). A late request has no right to a reply. A reply that would change the document must be issued as an addendum; a reply that only explains existing wording does not amend it.
Can a competitor see who asked the question?
No. Regulation 12(2) and the standard ITT require the entity to describe the inquiry without identifying its source. Competitors see the question and the answer, so a bidder writes the question in a way that discloses nothing about its own product, price or delivery plan.
What if an addendum arrives two days before the deadline?
The entity may extend the deadline to give tenderers time to take the addendum into account, but it is not obliged to. If no extension follows, the bidder re-prices in the time left or requests an extension through NeST. A bid submitted on the old document deviates from the amended one.
Does an addendum bind a bidder who never opened it in NeST?
Yes. Regulation 12(4) makes the addendum binding on every tenderer to whom the documents were provided once it is communicated through the system. The NeST notifications are the record of communication, so the bid manager checks the tender's notice log every working day until submission.
Can the bidder withdraw or replace its bid after an addendum?
Before the deadline, yes. The standard ITT allows a tenderer to modify or withdraw its tender before the submission deadline, and the NeST guidelines say a submitted tender may be revised in the system before then. After the deadline only an arithmetic correction, concurred by the bidder, can alter the figures.
May the committee ask a bidder to supply a missing document?
Only for a non-material gap in a tender that is already substantially responsive, and never on price. ITT 28.5 of PPRA's 2022 goods document allows a request for information to cure a non-material nonconformity. A missing manufacturer's authorisation listed as a requirement is usually material and cannot be added later.
Who signs the clarification request and the reply to the committee?
The person authorised to bind the company for that tender: the managing director, or the attorney named in the power of attorney for tender signing, using the company's registered NeST user. A reply signed without authority invites a further query and an argument that the company never confirmed the point.