Tender price schedule Tanzania: how the evaluation committee corrects, converts and compares the financial bid

The lowest price read at tender opening is not the price that wins. The evaluation committee corrects arithmetic line by line, applies discounts, converts currencies at the Bank of Tanzania rate, strips or adds taxes as the tender document directs and loads any preference margin. This guide reads the Act, the 2024 Regulations and PPRA's standard tender documents, and works one supply tender through to award and cash.

CPA Altho MwangoaChief Financial Officer, Zatra Consultants Limited
17 November 2026Published
26 November 2026Updated
20 min4,458 words
On this page
  1. What the law says
  2. Who should read this
  3. What must the price schedule, bill of quantities or activity schedule contain?
  4. How does the evaluation committee correct arithmetic errors?
  5. How are VAT, withholding tax and other taxes treated in the bid price?
  6. How does the committee convert currencies and apply discounts and preference?
  7. What is the lowest evaluated cost, and when is a bid abnormally low?
  8. Where the financial bid fails
  9. Worked example: a TZS 111 million computer supply tender with one arithmetic error
  10. Mainland and Zanzibar
  11. What to do now
  12. Key dates
  13. What the NEMBO desk prepares
  14. How Zatra helps
  15. Sources and status
  16. Frequently asked questions
Quick answer

How does an evaluation committee treat the tender price schedule in Tanzania?

A tender price schedule Tanzania procuring entities evaluate is checked line by line. Where unit price and total disagree the unit price governs. Where figures and words disagree the words govern. A tenderer who refuses the corrected total is rejected. Prices are compared net of VAT where the document says so, converted at the Bank of Tanzania rate 28 days before the deadline, then ranked after discounts and preference.

Cover: a tender price schedule with corrected line totals, VAT and the Form of Tender

What the law says

A tender price schedule Tanzania procuring entities evaluate is a legal document, not a quotation. The Public Procurement Act, 2023 (Act No. 10 of 2023) took effect on 17 June 2024 under Government Notice No. 455 of 7 June 2024, as PPRA announced on 12 June 2024. Section 3 defines the lowest evaluated tender as "the tender with the lowest price after consideration of all relevant factors", provided those factors were specified in the tender documents. Section 89(1) directs the evaluation committee to evaluate tenders "on a common basis" and adds that "the lowest submitted price, may not necessarily be the basis for selection for award of a contract". Daily News reported on 27 December 2025 that the framework brings benchmark prices and requires justification for price variations.

The Public Procurement Regulations, 2024 (GN 518 of 2024, dated 28 June 2024) commenced on 1 July 2024 and run to 362 regulations. The English version is GN 261 of 2025. Regulation 16 lets a procuring entity reject an abnormally low tender after asking for an explanation. Regulation 23(7)(b) lists "disagreement with arithmetical corrections made in the tender price" among the events a tender security may be tied to. The index also names regulations on examination of tenders (210), responsiveness (213), the lowest evaluated tender (220), conversion of currency (222), exchange rates (223) and the price adjustment formula (197). Their operative text could not be opened for this guide and is marked for confirmation.

The working rules sit in the PPRA Standard Tendering Document for General Goods and the Standard Tendering Document for Small Works, February 2022 editions still listed by PPRA on 17 November 2026. Their Instructions to Tenderers (ITT) say how prices are quoted, corrected, converted and compared. PPRA's Guidelines for Preparing and Submitting Responsive Tenders, 2026 restate the tenderer's side. On tax, the VAT Act Cap. 148 R.E. 2023 sets the Mainland rate at eighteen percent in section 5(1), and section 38(1) makes any price "advertised or quoted by a registered person" VAT inclusive.

Who should read this

This guide is for the managing director, the finance lead and the tender officer of a firm that bids through NeST, and for the CPA who reviews the financial bid before upload. It assumes the tenderer holds NeST registration (TZS 100,000 a year, F0174) and has paid the participation fee (TZS 30,000 national or TZS 500,000 international, F0175; TZS 10,000 for common-use items, NEW-01-47). The guide on NeST registration and the tender file covers that stage.

What must the price schedule, bill of quantities or activity schedule contain?

Goods tenders use a price schedule: one line per item with quantity, unit price and line total, and taxes shown as the ITT directs. Works tenders use a bill of quantities (BoQ) with rates against measured items, provisional sums and daywork. Non-consultancy services use an activity schedule. Each ends in a Form of Tender stating the total in figures and in words.

The goods STD is strict on completeness. ITT 15.2 reads: "Items not listed in the Price Schedule shall be assumed to be not included in the Tender." Under ITT 15.3 the tender price is "the total price of the Tender, excluding any discounts offered". ITT 15.9 fixes prices for the life of the contract unless the Tender Data Sheet allows adjustment.

The works STD treats an unpriced item differently. ITT 15.2 of the small works document says items with no rate "will not be paid for by the PE when executed" and are deemed covered by the other rates. It adds that "failure to quote for a major item in the tender will form a justifiable ground for rejection of tender". PPRA's 2026 guidelines add "proper signing of the tender form and price schedules" by the authorised person (paragraph 11.1(a)) and "to quote for all items in the package" (paragraph 12.1(b)).

What must the price schedule, bill of quantities or activity schedule contain?
ProcurementFinancial formUnpriced itemTaxes shown
GoodsPrice scheduleTreated as not offered; rejection riskSeparate line for taxes payable on award
WorksBill of quantitiesNot paid; major item rejectsInside the rates at 28 days before deadline
Non-consultancy servicesActivity scheduleFollow the ITT in the documentAs the Tender Data Sheet states
AllForm of TenderTotal in figures and words; signedDiscounts stated separately

How does the evaluation committee correct arithmetic errors?

The committee checks every line before it compares anything. The goods STD (ITT 30) and the works STD (ITT 29) set the same hierarchy. Where unit price and line total disagree, "the unit price shall prevail, and the total price shall be corrected". The exception is an obvious misplaced decimal point, where the line total stands and the unit price is corrected. Where subtotals and the grand total disagree, "the subtotals shall prevail and the total shall be corrected". Where figures and words disagree, "the amount in words shall prevail", unless the words carry an arithmetic error that the first two rules already fix.

The correction is then put to the tenderer. ITT 30.2 of the goods document is blunt: "If the Tenderer does not accept the corrected amount, its Tender will then be rejected." Refusal also engages the tender security under regulation 23(7)(b). A tenderer who cannot live with a corrected figure has one clean option: withdraw before the deadline, not after.

How does the evaluation committee correct arithmetic errors?
DiscrepancyWhat governsException
Unit price versus line totalUnit price; total correctedObvious misplaced decimal: total governs
Subtotals versus grand totalSubtotals; grand total correctedNone stated
Figures versus wordsWordsWords carry an arithmetic error already corrected
Tenderer refuses correctionTender rejectedTender security at risk (regulation 23(7)(b))

How are VAT, withholding tax and other taxes treated in the bid price?

Three tax layers touch the financial bid. First, VAT. A VAT-registered tenderer quotes a VAT-inclusive price by law (VAT Act section 38(1)), so the schedule shows the net amount, the 18 percent VAT and the gross total. TRA's VAT page confirms the 18 percent rate and a return due "on or before the 20th day of the following month" (F0245). The goods STD, in ITT 32.5, excludes from the comparison "sales and other similar taxes" payable on local goods if the contract is awarded, and customs duties on goods from abroad. In practice the committee compares net-of-tax prices for goods; the Tender Data Sheet in hand governs.

Second, income tax withholding on the payment. TRA's withholding tax page lists 5 percent on service fees paid to residents, 15 percent to non-residents, and 2 percent on "payments for goods supplied to Government and its institutions by any person". The Income Tax Act Cap. 332 R.E. 2023, section 106, carries the service fee rule. TRA's Practice Note 01/2019 extends the 2 percent goods rule to resident corporations "wholly or substantially financed" by Government. Withholding is not a cost but tax paid in advance, credited in the annual return, so the bid must not be inflated to recover it. See the guide on withholding tax certificates and the Zatra note on withholding tax on local payments.

Third, duties and levies inside works rates. ITT 15.3 fixes them at 28 days before the deadline, and GCC 56.1 lets the Project Manager adjust the contract price "if taxes, duties, and other levies are changed" after that date. The Zatra guide on the tax invoice for VAT covers the invoice after award.

How are VAT, withholding tax and other taxes treated in the bid price?
TaxRateWhere it appears in the bidSource
VAT, Mainland18 percentSeparate line; gross total in Form of TenderVAT Act s.5(1), s.38(1)
VAT, Zanzibar15 percentZanzibar tenders onlyZRA; F0246
Withholding, goods to Government2 percent of paymentNot in the price; deducted on paymentTRA withholding page
Withholding, service fees5 percent resident; 15 percent non-residentNot in the price; deducted on paymentITA Cap. 332 s.106; TRA
Duties and levies, worksAs at 28 days before deadlineInside the BoQ ratesSmall works ITT 15.3

How does the committee convert currencies and apply discounts and preference?

Goods supplied from within Tanzania are quoted in shillings (goods ITT 16.1(a)); goods from abroad may be quoted in up to three freely convertible currencies. For comparison, ITT 16.2 and ITT 31.1 convert foreign amounts to shillings at the Bank of Tanzania selling rate on the date 28 days before the submission deadline. The 2022 goods document prints "twenty-eight (280) days" in ITT 31.1, an evident typing error, so the Tender Data Sheet should state the date and source. The Bank of Tanzania's past exchange rates tool gives the rate for any date. A USD 50,000 component at an illustrative selling rate of TZS 2,600 enters the comparison at TZS 130,000,000.

Discounts count only if stated in the Form of Tender with the method of application (ITT 15.4). The committee applies them after arithmetic correction and before ranking (goods ITT 32.2(c)), and only once any stated condition is met.

Preference is applied last. PPRA's Preference Scheme Guidelines, 2025 (effective 23 January 2025, under regulation 38(4)) set a 15 percent margin for goods manufactured, mined or produced in Tanzania (clause 9.1) and 10 percent for local contractors and service providers (clause 7.3(a)). The margin is added to the foreign tender's price for ranking only (clause 7.9(a)): a foreign goods offer of TZS 90,000,000 becomes TZS 103,500,000, so a local offer at TZS 100,000,000 ranks first. The guide on the margin of preference works through the groups.

What is the lowest evaluated cost, and when is a bid abnormally low?

Lowest evaluated cost is the net result of the chain above: the price read at opening, corrected for arithmetic, adjusted for discounts, converted to shillings, adjusted for any quantifiable minor deviation and loaded with any preference margin. Goods ITT 34.1 awards to the tender "with the lowest evaluated price" among those that are eligible, compliant and substantially responsive. Section 87(2) of the Act requires any factor beyond price, such as operating cost or delivery time, to be specified in the tender document with the way it is quantified.

A price can also be too low. Regulation 16(1) says a procuring entity "may reject a tender if it considers it to be of abnormally low price", and regulation 16(5) defines that as a price that does not provide "a margin for normal level of profit". Before rejection the entity must request an explanation, "take into account the evidence provided" and verify the suspect parts (regulation 16(2)). The decision and its grounds are recorded and sent to the tenderer (regulation 16(3)). A tenderer with a sharp price should hold a cost build-up ready. The guide on tender evaluation criteria covers the technical side.

Where the financial bid fails

Most financial bids fail on form, not on price. PPRA's 2026 guidelines record that the lowest price read at opening "does not necessarily represent the lowest evaluated tenderer" (paragraph 8.1). Deviation from the commercial terms "shall amount to rejection of the tender" (paragraph 11.2).

Where the financial bid fails
DefectConsequenceClause
Required item left unpriced in a goods scheduleItem treated as not offered; rejectionGoods ITT 15.2; Guidelines 2026, 12.1(b)
Major BoQ item left unpricedRejectionSmall works ITT 15.2
Form of Tender unsigned or signed without authorityRejectionGuidelines 2026, 11.1(a)
Discount stated outside the Form of TenderIgnoredGoods ITT 15.4
Price without a profit marginExplanation demanded; possible rejectionRegulation 16
Tender security short of validity plus 28 daysRejectionRegulation 24; Guidelines 2026, 14.2

A dispute over a correction or a rejection runs through the Act's complaint and appeal route, with an advocate instructed for the Public Procurement Appeals Authority; see the guide on the PPAA appeal file.

Worked example: a TZS 111 million computer supply tender with one arithmetic error

A regional hospital invites national tenders through NeST for 40 desktop computers, 40 monitors and installation. The figures are illustrative; the rules are those of the goods STD.

Tenderer A's schedule reads: item 1, 40 desktops at TZS 1,850,000, total TZS 74,000,000; item 2, 40 monitors at TZS 420,000, total written as TZS 18,600,000; item 3, installation, TZS 3,500,000. The subtotal as submitted is TZS 96,100,000, VAT at 18 percent TZS 17,298,000, and the Form of Tender states TZS 113,398,000 in figures and in words. Tenderer B quotes TZS 94,900,000 net and TZS 111,982,000 gross, with a 2 percent discount in the Form of Tender if all three items are awarded. Tenderer C quotes TZS 90,500,000 net and TZS 106,790,000 gross, but leaves item 3 blank. At opening, C is read lowest, B second, A third.

The arithmetic check finds that 40 monitors at TZS 420,000 is TZS 16,800,000, not TZS 18,600,000. Under ITT 30.1(a) the unit price governs. A's corrected subtotal is TZS 74,000,000 plus TZS 16,800,000 plus TZS 3,500,000, which is TZS 94,300,000. VAT becomes TZS 16,974,000 and the corrected total TZS 111,274,000. The amount in words does not rescue the original figure, because the words repeat the same error (ITT 30.1(c)). Tenderer A is asked to accept TZS 111,274,000 and does.

Tenderer C's blank item 3 is a required item with no price. Under ITT 15.2 it is assumed not to be included, so the tender is rejected. Tenderer B's discount condition is met because the hospital awards one contract, so B's comparison price is TZS 94,900,000 less TZS 1,898,000, which is TZS 93,002,000. Comparing net of VAT under ITT 32.5, Tenderer B at TZS 93,002,000 ranks first and Tenderer A at TZS 94,300,000 second, a gap of TZS 1,298,000. Without the discount, A's corrected price would have beaten B by TZS 600,000. The correction cost A TZS 2,124,000 of headline price; the discount decided the award.

Worked example: a TZS 111 million computer supply tender with one arithmetic error
TendererRead at opening (gross)After correction (net)After discount (net)Result
ATZS 113,398,000TZS 94,300,000TZS 94,300,000Second
BTZS 111,982,000TZS 94,900,000TZS 93,002,000Lowest evaluated
CTZS 106,790,000Item 3 unpricedNot comparedRejected

The contract with Tenderer B is signed at TZS 93,002,000 plus VAT TZS 16,740,360, a gross TZS 109,742,360. Costs outside the bid follow. The agreement carries stamp duty of TZS 2,000 (F0267). NeST levies a monitoring fee of TZS 500,000 on the winning tenderer for a contract between TZS 100 million and TZS 500 million (NEW-01-49); whether the bracket reads the gross or the net sum should be confirmed on NeST. The hospital withholds 2 percent on the goods: on the net TZS 93,002,000 that is TZS 1,860,040, leaving cash of TZS 107,882,320 and a tax credit of TZS 1,860,040. The output VAT of TZS 16,740,360 goes into B's return by the 20th of the following month. The guide on performance security and payment claims continues from signing.

Worked example: a TZS 111 million computer supply tender with one arithmetic error
Item after awardAmountBasis
Contract price, grossTZS 109,742,360TZS 93,002,000 plus 18 percent VAT
Stamp duty on the agreementTZS 2,000F0267
NeST monitoring feeTZS 500,000NEW-01-49, TZS 100m to 500m bracket
Withholding on goods, 2 percentTZS 1,860,040On the net sum; tax credit, not cost
Output VAT to declareTZS 16,740,360VAT return by the 20th (F0245)
Tax clearance certificate, if requestedNo fee publishedNEW-02-18

Mainland and Zanzibar

Everything above is Mainland law. Zanzibar runs its own system under the Public Procurement and Disposal of Public Assets Act, No. 11 of 2016, administered by the Zanzibar Public Procurement and Disposal of Public Assets Authority (ZPPDA). A Bill published on 5 November 2024 proposes to repeal the 2016 Act and establish a Zanzibar Public Procurement Regulatory Authority; whether it has been enacted is unknown from the sources read. PPRA reported on 9 February 2025 that Zanzibar is revising its procurement law and building its own electronic system, so NeST does not reach Zanzibar tenders. Zanzibar VAT is administered by the Zanzibar Revenue Authority at 15 percent, with a registration threshold of TZS 100 million a year (F0246), so a Zanzibar price schedule shows 15 percent. Income tax, including withholding, is a Union matter collected by TRA on both sides.

What to do now

  1. Read the ITT and Tender Data Sheet first. Note the currency clause, the exchange rate date, fixed or adjustable prices, preference and how taxes are shown. The Tender Data Sheet overrides the general ITT wording.
  2. Build the schedule with formulas. Every line total is quantity times unit price, every subtotal a sum of lines, VAT a formula on the net subtotal.
  3. Price every required item. A blank line in a goods schedule means the item is not offered. In a BoQ, an unpriced major item is a rejection.
  4. Write the total in words from the final figure. The words govern, so they are typed last and checked by a second person.
  5. Put discounts in the Form of Tender only. State the percentage, the base and the condition.
  6. Keep a cost build-up. If the price is below the entity's estimate, the committee may invoke regulation 16. A one-page margin analysis answers it.
  7. Check the tender security against validity plus 28 days. See the guide on the tender securing declaration or bid security.
  8. Have a CPA sign off the tax lines. Confirm VAT registration status, the 18 percent computation and the cash effect of withholding. Then upload through NeST before the deadline, not at it.

Key dates

Key dates
EventTimingSource
Exchange rate and tax base date28 days before the submission deadlineGoods ITT 16.2; small works ITT 15.3, 16.2
Tender security validityTender validity plus at least 28 daysRegulation 24
Release of unsuccessful tenderers' securitiesWithin 30 daysRegulation 25
Complaint after notice of intention to awardShort window stated in the notice; confirm the daysAct s.69
Performance securityBy the date in the Letter of AcceptanceSmall works GCC 62.1
Payment of a certified amountWithin 28 days of certificationSmall works GCC 53.1
VAT return and paymentBy the 20th of the following monthVAT Act; F0245

Price adjustment after award applies only where the Special Conditions provide for it (GCC 57.1); otherwise the rates are "deemed to include amounts to cover the contingency" of cost rises (GCC 57.2). PPRA's Guidelines for Price Adjustment in Public Procurement, 2026 could not be read here, so their thresholds and indices are unknown.

What the NEMBO desk prepares

NEMBO designs and delivers the tender and investor document pack: the price schedule, BoQ or activity schedule laid out to the entity's form, the Form of Tender with figures and words reconciled, and the cost build-up for an abnormally low price query. Zatra Consultants prepares and checks the content: line totals and VAT against the formulas, the currency clause against the Bank of Tanzania rate, and the tax lines against the tenderer's VAT and withholding position. The free tender evidence index lists the supporting documents by clause.

Two cost buckets stay separate. Government fees are paid at the official rate and passed through at cost: NeST registration (F0174), tender participation (F0175 or NEW-01-47), stamp duty on the agreement (F0267), the monitoring fee by contract value (NEW-01-49) and any tax clearance certificate (NEW-02-18). NEMBO's and Zatra's fees are quoted separately on the pricing page. NEMBO does not decide or guarantee any authority's outcome, nor any bank's or tender panel's; the evaluation committee does, on the document it receives.

How Zatra helps

The studio process and the packages page set out how a tender brief becomes a checked financial bid and a formatted price schedule. Zatra Consultants runs the tender and procurement advisory desk: ITT reading, pricing review, the arithmetic and tax check before upload, and the response to a correction letter or an abnormally low price query. Its note on registering as a government supplier covers the NeST side. Tax positions are confirmed with a CPA; a rejection dispute goes to an advocate. To start, use the start page.

Next step

Investor documents and tender files

Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.

Open the desk page

Sources and status

Accurate as at 17 November 2026. The arithmetic, currency, discount and abnormally low tender rules were read verbatim in the PPRA standard tendering documents of February 2022, in regulations 16 and 23 of the 2024 Regulations and in Act sections 3, 87 and 89. Regulations 197, 210, 213, 220, 222 and 223 could not be opened beyond their headings and are marked for confirmation. PPRA's Price Adjustment Guidelines 2026 are a scanned image and were not read. The worked example and the TZS 2,600 exchange rate are illustrative; the Zanzibar Bill's enactment status is unknown.

Figures to confirm before you act

  • Regulations 197, 210, 213, 220, 222 and 223 were read only as index headings in GN 261 of 2025. Confirm their operative wording before citing them in a complaint.
  • ITT 16.2 of the 2022 goods document sets the exchange rate date at 28 days before the deadline, while ITT 31.1 prints 280 days. Confirm the date and source in the Tender Data Sheet.
  • Whether the committee compares prices net of VAT depends on ITT 32.5 and the Tender Data Sheet of the specific tender. Confirm before presenting the VAT line.
  • The 2 percent withholding on goods supplied to Government and the 5 percent on resident service fees are from TRA's withholding tax page. Confirm the base, net or gross of VAT, with a CPA and section 106 of the Income Tax Act Cap. 332 R.E. 2023.
  • The NeST monitoring fee brackets (NEW-01-49) come from the Zatra fee register at 26 September 2026. Confirm on NeST whether the bracket reads the gross or the net contract sum.
  • The complaint window after the notice of intention to award under section 69 of the Act was not read in full. Confirm the number of working days in the notice.
  • The status of the Zanzibar Public Procurement Bill of 5 November 2024 is unknown. Confirm with ZPPDA whether the 2016 Act still governs.

This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.

Frequently asked questions

Does the unit price or the total price govern when they disagree?

The unit price governs and the line total is corrected, under ITT 30.1(a) of the PPRA goods document and ITT 29.1(a) of the works document. The one exception is an obvious misplaced decimal point in the unit price, where the line total stands. Subtotals likewise govern over a wrong grand total.

Can a tenderer refuse an arithmetic correction?

A tenderer may refuse, but the tender is then rejected under ITT 30.2 of the goods document. Regulation 23(7)(b) of the 2024 Regulations also lists disagreement with arithmetical corrections among the events a tender security may be tied to. The correction is accepted in writing within the time given, or the tender is lost.

Should the tender price include VAT?

A VAT-registered tenderer quotes a VAT-inclusive price because section 38(1) of the VAT Act makes any quoted price VAT inclusive. The schedule shows the net amount, the 18 percent VAT and the gross total on separate lines. Goods ITT 32.5 then excludes taxes payable on award from the comparison. A tenderer below the registration threshold shows no VAT.

Which exchange rate does the committee use for a foreign currency bid?

The Bank of Tanzania selling rate for similar transactions on the date 28 days before the submission deadline, under ITT 16.2 and 31.1 of the goods document and ITT 16.2 and 30 of the works document. The Tender Data Sheet names the source and date, and the tenderer should look up the same rate before submission.

What happens if an item is left unpriced?

In a goods schedule the item is assumed not to be included, and a required item missing from the offer leads to rejection. In a bill of quantities an unpriced item is not paid for when executed and is deemed covered by the other rates. A major item left unpriced is a ground for rejection under small works ITT 15.2.

What is an abnormally low tender and how is it handled?

Regulation 16 of the 2024 Regulations defines it as a price that does not provide a margin for a normal level of profit. The procuring entity must ask for a written explanation, weigh the evidence and verify the suspect parts before rejecting, and must record its grounds. A cost build-up with supplier quotes answers the request.

Is withholding tax a cost the tenderer should add to the price?

No. The 2 percent withheld on goods supplied to Government and the 5 percent withheld on resident service fees are income tax paid in advance. The payer issues a withholding certificate and the tenderer claims the credit in its annual return. Pricing it in inflates the bid; cash flow planning is the right response.

Does the Mainland price schedule rule apply to a Zanzibar tender?

No. Zanzibar procurement runs under its own Public Procurement and Disposal of Public Assets Act, No. 11 of 2016, administered by ZPPDA, and a repeal Bill of November 2024 has an unknown status. Zanzibar VAT is 15 percent under ZRA, and the Zanzibar document's own correction and currency clauses apply.

CPA Altho Mwangoa

Chief Financial Officer, Zatra Consultants Limited. Written and checked by CPA Altho Mwangoa, who reviews the sources, the figures and the legal positions before a note is published. NEMBO designs and publishes it.

Related reading

Notes from the studio, with the working shown.

Tender Evaluation Criteria Tanzania: How Bids Are Scored: cover
Investor documents17 min read

Tender Evaluation Criteria Tanzania: How Bids Are Scored

A consultancy bid scoring 90 technical and 75 financial can beat a cheaper rival at an 80:20 weighting. See the panel's steps, the five working day complaint window and a worked scorecard.

By NEMBO Studio and Zatra Consultants · 6 November 2026
Tender security or securing declaration: how a bidder decides: cover
Investor documents7 min read

Tender security or securing declaration: how a bidder decides

PPRA's criteria split tender security from a securing declaration at TZS 2 billion and TZS 10 billion. What each risks and how the validity date is counted.

By NEMBO Studio and Zatra Consultants · 17 October 2026
Performance Security Tanzania: NeST Contract to Payment: cover
Investor documents20 min read

Performance Security Tanzania: NeST Contract to Payment

The award is not the contract and the contract is not the payment. What the Public Procurement Act 2023, the 2024 Regulations and the NeST guidelines require of a winning bidder at each step, with the days and the deductions.

By NEMBO Studio and Zatra Consultants · 11 November 2026
Tender Clarification Tanzania: Request, Addendum, Bid: cover
Investor documents19 min read

Tender Clarification Tanzania: Request, Addendum, Bid

A tender clarification is a written question to a procuring entity through NeST, and an addendum is the entity's binding change to the tender document before the deadline. Both are governed by the Public Procurement Act, 2023, the Public Procurement Regulations, 2024 and the Instructions to Tenderers in PPRA's standard documents. This guide sets out the request letter, the clarification window, the pre-tender meeting, what an addendum can change, how the Form of Tender acknowledges it, what an evaluation committee may ask after submission, and the file a bidder keeps, with a dated December 2026 example.

By NEMBO Studio and Zatra Consultants · 26 November 2026