On this page
- What the law says
- Who should read this
- What must the investment progress report show?
- What evidence file sits behind each line?
- How do TISEZA and a bank read it?
- How does the report link to the TRA side and the annual report?
- Which faults get a report queried?
- Who prepares, reviews, signs and files it?
- Worked example: Kibaha Packaging Limited, June 2026
- Mainland and Zanzibar: which rules differ?
- What to do now
- Key dates
- What the NEMBO desk prepares
- How Zatra helps
- Sources and status
- Frequently asked questions
What must an investment progress report show in Tanzania?
An investment progress report is the implementation report a certificate holder files with TISEZA under section 32(d) of the Investment and Special Economic Zones Act, No. 6 of 2025. It shows project identity, milestones against the application plan, capital invested with bank evidence, employment and permits, incentives used, construction and production status, and problems. Regulation 27 of GN No. 466 of 2025 sets a yearly Form No. 5.

What the law says
An investment progress report is the implementation report a certificate holder files with the Tanzania Investment and Special Economic Zones Authority (TISEZA). The duty sits in section 32(d) of the Investment and Special Economic Zones Act, No. 6 of 2025. Section 32 lists the obligations of an investor, and paragraph (d) reads: "to submit to the Authority report on the implementation and progress of investment project within the specified time frame". The Act does not fix the frequency.
The sanction is in section 17(2)(e). The Authority may revoke a certificate or licence where the investor "has not submitted reports on the implementation and progress of the investment project for twenty-four consecutive months". The same subsection covers failure to start the project within twelve months of issue without valid reason. Section 31 gives the Government the right to supervise investment activities, and section 32(f) obliges the investor to allow Authority officers to monitor progress. Section 45(3)(a) makes it an offence to knowingly or recklessly give false or misleading information; section 45(3)(d) covers using incentives for purposes other than those intended. The penalty read in the PDF is a fine of TZS 5,000,000 to TZS 50,000,000, or imprisonment of six months to five years, or both. Section 46, the general penalty, is a fine of TZS 2,000,000 to TZS 5,000,000, or imprisonment of six months to two years, or both.
The time frame is in the Investment and Special Economic Zones Regulations, 2025, Government Notice No. 466 of 25 July 2025, made under section 50 and published in Swahili. Regulation 27, headed "Taarifa ya mwaka ya mwekezaji", as read on 25 November 2026, requires a certificate holder to submit a report on the progress of project implementation every year, on Form No. 5 of the First Schedule, with the fee set in the Second Schedule. Regulation 68(1)(e) repeats the 24-month cancellation ground. Zone operators file quarterly under regulation 41(1)(k). The UNCTAD Investment Policy Monitor and DoingBusiness (16 September 2025) record the gazettement; neither describes the reporting duty.
Three cycles are in circulation. TISEZA's procedures portal lists a service called "Submit bi-annual progress report". Invest Tanzania, on 2 May 2026, reported a TISEZA notice requiring quarterly reports, with second-quarter reports due on or before 30 June 2026; that notice was not found on tiseza.go.tz on 25 November 2026. The safe reading: the Regulations specify a yearly Form No. 5 and TISEZA may call for more. Confirm the cycle and the form with TISEZA before the first filing.
Section 2(1) excludes investors under the Mining Act, oil investors under the Petroleum Act, and investors in hazardous chemicals, weapons or explosives. The hook for this guide is a statement reported by The Respondent on 10 November 2026: a TISEZA investment promotion manager said an investor who submits all required documents can obtain a certificate within 24 hours through the One-Stop Centre. A fast certificate starts the reporting clock fast. The Zatra operating guide to the Act covers registration, incentives and revocation.
Who should read this
Read this if the company holds a certificate of investment, or a certificate of incentives issued under the repealed Tanzania Investment Act 2022, which section 51(2)(a) keeps in force. The roles that act on it are the finance manager, the company secretary who files, the project manager, the HR officer and the director who signs. A consultant preparing the report, and a lender reading it as drawdown evidence, will use the evidence table and the worked example.
Skip this if the company has no TISEZA certificate or licence, or is excluded by section 2(1). A Zanzibar project registered with ZIPA reads the Mainland and Zanzibar section and then takes the Zanzibar instrument to an advocate.
What must the investment progress report show?
Neither section 32(d) nor regulation 27 lists the contents, and Form No. 5 could not be read on tiseza.go.tz on 25 November 2026. The contents below are what TISEZA's monitoring function needs to compare against the application, whatever the form asks.
Project identity
Company name, BRELA number, TIN, certificate number, date of issue and expiry, the registered activity and location, and the approved project value in USD and TZS. Regulation 15(1) gives a certificate a five-year life. Any change under section 18 (cessation, successor, change of name or particulars, expansion) is flagged with the date of the written notice.
Milestones against the application plan
The report repeats each milestone in the application's implementation plan, its planned date, its actual date or status, and the slippage in months with a one-line reason. A milestone with no document beside it is an assertion, not progress.
Capital invested to date
A table by category with the approved amount, the amount invested in the period, the cumulative amount and the balance to complete, in USD and TZS with the rate basis stated. Foreign capital is shown by tranche with the value date on the bank credit advice, since the receiving bank is the only party that creates a contemporaneous record of the money. Loans are shown by drawdown notice.
Employment
Jobs planned, jobs created to date, split Tanzanian and foreign, permanent and casual, and by gender where the form asks; section 32(c) obliges the investor to promote gender equality and skills development. For foreign staff: name, role, permit type, number and expiry, against the number limits that section 36 refers to.
Incentives used
The certificate schedule of plant, each TRA exemption approval, each customs entry cleared under it, the customs value, and the duty and VAT relieved. Section 45(3)(d) makes misuse an offence, so the relieved assets must be on site and in use.
Land, construction, production and problems
Land tenure, construction status with the contractor's certificate and dated photographs, and, where operating, production volumes, sales and exports. The final section is problems and requests: delays, permits outstanding, any request for an extension of time or amendment.
What evidence file sits behind each line?
The file is what survives a monitoring visit under section 31(2) and a bank's drawdown check.
| Report section | Evidence document | Who holds it |
|---|---|---|
| Project identity | Certificate, BRELA certificate, TIN certificate, section 18 notices | Company secretary |
| Milestones | Implementation plan, building permit, completion certificate, commissioning report, dated photographs | Project manager |
| Capital invested | Bank credit advices and MT103 messages, loan drawdown notices, supplier invoices, fixed asset register | Finance manager |
| Funding | Return of allotment at BRELA, board resolution, loan agreement | Company secretary |
| Employment | Payroll register, NSSF contribution returns, contracts, work and residence permits | HR officer |
| Incentives used | Certificate schedule of plant, TRA exemption approvals, customs entries, disposal permissions | Finance manager |
| Land and construction | Title or lease, building permit, environmental certificate where required, interim payment certificates | Project manager |
| Production and sales | Production log, EFD or VFD sales summary, VAT returns, export entries | Finance manager |
| Problems and requests | Correspondence with TISEZA, extension or amendment letters | Company secretary |
The fixed asset register ties every capital figure to an invoice, a customs entry and a location, and the payroll register ties every job claimed to a person, a contract and an NSSF number.
How do TISEZA and a bank read it?
TISEZA reads the report as a monitoring input. Under regulation 26 the Authority monitors and evaluates registered projects, reports to its Board every quarter and to the Minister every year. The officer compares the report with the application: approved against invested value, planned against created jobs, scheduled plant against plant cleared under exemption. A project behind plan with a documented reason and a request is facilitated; section 13(2) obliges other institutions to respond within seven working days to a request the Authority forwards. A project with no report for 24 consecutive months, or with figures that contradict the application, faces section 17(2) and section 45(3)(a). The July to September 2026 figures (209 projects, USD 2.81 billion) are commitments; implementation reports measure delivery.
A bank reads the same report as cost-to-complete evidence: how much of the approved project is in the ground, how much equity has arrived through the bank, and whether the next drawdown is covered. The sources and uses guide shows the table a credit committee expects, and the project progress report guide shows how a lender tests the milestone narrative.
How does the report link to the TRA side and the annual report?
Relief on capital goods runs in two steps: TISEZA issues the certificate with its schedule of plant, and TRA's Commissioner General approves the relief against that schedule before the goods are declared. The Zatra capital goods relief guide (15 September 2026) notes that relieved assets cannot be sold, leased or moved to another project without the Commissioner's written permission. The incentives table should agree, entry by entry, with the fixed asset register.
A manufacturer that also imports inputs under the East African Community duty remission scheme files a quarterly return with TRA. A TRA notice of 1 October 2026 gave 31 October 2026 as the first date, as reported in the Zatra note on duty remission returns. The production and export figures in that return and in the TISEZA report must match; the duty remission file guide covers the TRA side. No TRA return on the use of TISEZA capital goods exemptions was found.
Cumulative capital invested should reconcile to additions to property, plant and equipment in the audited accounts, and the foreign capital tranches to issued share capital at BRELA. The company annual report guide sets out the directors' report that carries the same story. Where they disagree, the audited figure wins and the report explains the difference.
Which faults get a report queried?
| Fault | What the reader sees | Fix |
|---|---|---|
| Capital in USD only | Cannot tie to TZS bank statements | Both currencies, rate on each credit advice |
| Milestones restated from the application | No actual dates, no slippage | Plan date, actual date, months late, cause |
| Jobs claimed exceed payroll | Casuals and contractor staff counted | Report each group separately |
| Foreign staff with expired permits | Breach of the section 36 limits | Permit numbers and expiry dates; renew first |
| Incentives table without entry numbers | Cannot match plant to relief claimed | Customs entry number against each asset |
| Photographs undated | Not evidence at the report date | Date, location and milestone on each image |
| No signature or filing receipt | Filing cannot be proved | Director signs; keep the acknowledgement |
| Section 18 changes not notified | Expansion surfaces in the report first | File the notice, then cite it |
The two faults that cause the most harm are unexplained slippage (section 17(2)(d)) and a capital figure that cannot be banked (section 45(3)(a)).
Who prepares, reviews, signs and files it?
Owner: the finance manager owns the report and its numbers. Contributors: the project manager for milestones and construction, the HR officer for employment and permits, the company secretary for identity, notices and filing. Reviewer: the external accountant checks the reconciliations to the fixed asset register, the bank, payroll and NSSF returns. Sign-off: a director signs the declaration, because section 45(3)(a) attaches to the person who gives the information. Version: version number, period covered, date signed and date filed. Filing: the company secretary files on the current form, pays the Second Schedule fee, and keeps the acknowledgement with the signed copy. Retention: the life of the certificate plus the periods in the record retention guide. Put the report on the compliance calendar so that it is never 24 months late.
Worked example: Kibaha Packaging Limited, June 2026
Kibaha Packaging Limited is an illustrative company. It holds a certificate of investment for a USD 2,400,000 corrugated packaging plant at Kibaha, issued in July 2024, and is reporting for the year to 30 June 2026, its second year. Every figure is illustrative, converted at an illustrative TZS 2,600 per USD; a real report uses the rate on each credit advice.
| Milestone | Plan in application | Status at 30 June 2026 | Evidence |
|---|---|---|---|
| Site lease registered | Month 3 (October 2024) | Done, October 2024 | Registered lease, rent receipts |
| Building permit | Month 5 (December 2024) | Done, January 2025 | Permit, approved drawings |
| Civil works complete | Month 12 (July 2025) | Done, October 2025, 3 months late | Completion certificate, dated photographs |
| Plant landed | Month 14 (September 2025) | Lines 1 and 2 landed; line 3 shipped | 14 customs entries, TRA approvals |
| Commissioning | Month 18 (January 2026) | Line 1 done March 2026; line 2 in progress | Commissioning report |
| Trial production | Month 20 (March 2026) | Started May 2026 on line 1 | Production log, first EFD sales |
| Commercial production | Month 24 (July 2026) | Expected October 2026; extension requested | Letter to TISEZA, revised plan |
The capital table shows 78 per cent of the approved project invested at the end of year two.
| Category | Approved (USD) | Invested to date (USD) | Invested to date (TZS) | Evidence |
|---|---|---|---|---|
| Site lease and site works | 150,000 | 150,000 | 390,000,000 | Lease, contractor invoices |
| Buildings and civil works | 820,000 | 790,000 | 2,054,000,000 | Payment certificates 1 to 9 |
| Plant and machinery | 1,050,000 | 640,000 | 1,664,000,000 | Invoices, customs entries |
| Vehicles and handling equipment | 110,000 | 110,000 | 286,000,000 | Invoices, registration cards |
| Pre-operating costs | 70,000 | 70,000 | 182,000,000 | Ledger, receipts |
| Working capital | 200,000 | 120,000 | 312,000,000 | Bank statements, stock count |
| Total | 2,400,000 | 1,880,000 | 4,888,000,000 | Fixed asset register, bank |
Funding of the USD 1,880,000 invested is foreign equity of USD 1,200,000 in three tranches, each backed by an MT103, a credit advice and a return of allotment at BRELA, a shareholder loan of USD 400,000 and a TZS term loan equivalent to USD 280,000. Employment: 54 staff against 86 planned, 49 Tanzanian and 5 foreign engineers with permits listed. Incentives used: 14 customs entries, customs value USD 610,000, duty and VAT relieved TZS 290,000,000. Problems and requests: civil works three months late, line 3 delayed by the supplier, and an extension of commercial production to October 2026 requested. A director signs; the company secretary files and keeps the receipt.
Mainland and Zanzibar: which rules differ?
The report described above is a Mainland instrument: TISEZA, Act No. 6 of 2025 and GN No. 466 of 2025 apply to Mainland Tanzania. Zanzibar runs its own authority, the Zanzibar Investment Promotion Authority (ZIPA), under Zanzibar law.
What was verified on 25 November 2026: ZIPA's investment certificate page states that the certificate is issued under section 23 of the Zanzibar Investment Promotion and Protection Act No. 14 of 2018, and that "the Certificate is renewed annually until all approved capital is invested", after which an Investment Service Licence applies. The Zanzibar Investment (General) Regulations, 2025 (Legal Notice No. 59 of 2025, gazetted 20 June 2025) name the Zanzibar Investment Act No. 10 of 2023 as their parent Act. Regulation 10(2) requires the Investment Service Licence annually, and regulation 12(2)(c) requires an "Investment progress report" with that application.
What was not verified: neither the 2018 Act nor the 2023 Act was read. A Zanzibar certificate holder should take the Zanzibar Investment Act and the 2025 Regulations to an advocate practising in Zanzibar before relying on this section. Zanzibar's domestic taxes run through the Zanzibar Revenue Authority, not TRA.
What to do now
- Confirm the cycle and the form: ask TISEZA for the current Form No. 5, the filing channel, the period counted and whether a half-yearly or quarterly report is called for.
- Pull the application file: retrieve the implementation plan, the approved project value and the plant schedule.
- Build the evidence file: assemble the nine folders in the evidence table, led by the fixed asset register and the payroll register.
- Reconcile the capital figure: tie cumulative capital invested to the fixed asset register, the bank and the last audited accounts.
- Check permits and notices: list every foreign employee's permit expiry, renew any that lapse before filing, and file any outstanding section 18 notice.
- Write the report from the file: identity, milestones, capital, funding, employment, incentives, construction, production, problems and requests.
- Review, sign and file: the accountant reviews the reconciliations, a director signs, the company secretary files, pays the Second Schedule fee and keeps the acknowledgement.
- Diarise the next one: put the next report, the certificate renewal and the TRA returns on the compliance calendar.
Key dates
Within twelve months of the certificate: the project must have started, or the Authority may revoke under section 17(2)(d). Every year: the Form No. 5 report under regulation 27, with the cycle and the period to be confirmed with TISEZA. Twenty-four consecutive months without a report: revocation ground under section 17(2)(e). Five years: certificate validity under regulation 15(1), with renewal on Form No. 4 at least three months before expiry under regulation 18(1). Quarterly, by the end of the month after the quarter: the EAC duty remission return to TRA for manufacturers in that scheme. The free NEMBO reporting framework places the report among the company's other periodic reports.
What the NEMBO desk prepares
The NEMBO financial reports desk prepares the investment progress report set: the report, the milestone and capital tables, the evidence index, the reconciliations, the declaration page and the filing record. Zatra Consultants prepares the content and Joseph Marwa reviews the file against the Act, the Regulations and the application before it goes to the director. Where the project also needs the investor pack, the investor documents desk prepares it to the same figures, so the report, the pack and the incentives file tell one story. Two cost buckets apply: government, bank or regulator charges are paid at the official rate and are separate from NEMBO's and Zatra's fees, which are published on the packages page and quoted in writing. The Form No. 5 fee is set by TISEZA's Second Schedule; see the Zatra government fees guide. NEMBO does not decide or guarantee any authority's outcome. The process page shows the steps from brief to filed document, and the start page shares the details.
How Zatra helps
Zatra Consultants handles the TISEZA side through its TISEZA investor registration service, keeps the figures through management accounts and financial reporting, and runs the permit position through work and residence permits. The registration file note and the TISEZA fees note cover the application and the Second Schedule. The horticulture investment file guide is a sector example. CPA Altho Mwangoa signs tax computations and audited figures where the report draws on them. Disputes, revocation proceedings, prosecutions under section 45, appeals to the Minister, formal legal opinions and anything before a court, tribunal, CMA or registry go to an advocate, as does the Zanzibar instrument.
Investment progress report set
Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.
Open the desk pageSources and status
Accurate as at 25 November 2026. Sections 2, 17, 18, 19, 31, 32, 36, 45, 46, 50 and 51 of the Investment and Special Economic Zones Act, No. 6 of 2025 were read in the TISEZA PDF. Regulations 14, 15, 18, 23, 26, 27, 41 and 68 of GN No. 466 of 2025 were read in the Swahili text on tiseza.go.tz. Form No. 5 and its fee were not read, and the quarterly and half-yearly cycles rest on Invest Tanzania and the TISEZA procedures portal. The Zanzibar Acts were not read; that section rests on ZIPA's website and the Zanzibar Investment (General) Regulations, 2025.
- 1The Investment and Special Economic Zones Act, 2025 (Act No. 6 of 2025)TISEZA, Act dated 4 March 2025, English translation published as GN No. 4 of 6 January 2026, read 25 November 2026. Accessed 25 November 2026.
- 2Kanuni za Uwekezaji na Maeneo Maalumu ya Kiuchumi za Mwaka 2025 (Investment and Special Economic Zones Regulations, 2025)TISEZA, Government Notice No. 466 of 25 July 2025, Swahili text, read 25 November 2026. Accessed 25 November 2026.
- 3TISEZA procedures portal: services to investorsTISEZA, live portal listing 'Submit bi-annual progress report', read 25 November 2026. Accessed 25 November 2026.
- 4United Republic of Tanzania issues Investment and Special Economic Zones RegulationsUNCTAD Investment Policy Monitor, measure recorded for 25 July 2025, source accessed by UNCTAD 3 September 2025. Accessed 25 November 2026.
- 5Tanzania gazettes new investment and special economic zones regulationsDoingBusiness Tanzania, 16 September 2025. Accessed 25 November 2026.
- 6TISEZA urges investors to tap into One-Stop Centre servicesThe Respondent, 10 November 2026. Accessed 25 November 2026.
- 7Tanzania Tightens Investment Oversight with Mandatory Quarterly ReportingInvest Tanzania, 2 May 2026, updated 7 May 2026; the TISEZA notice it describes was not found on tiseza.go.tz. Accessed 25 November 2026.
- 8ZIPA: Investment CertificateZanzibar Investment Promotion Authority, read 25 November 2026. Accessed 25 November 2026.
- 9Zanzibar Investment (General) Regulations, 2025ZIPA, Legal Notice No. 59 of 2025, gazetted 20 June 2025, read 25 November 2026. Accessed 25 November 2026.
- 10Investment and Special Economic Zones Act 2025: operating guide to what the statute changedZatra Consultants, 10 September 2026, reviewed 26 October 2026. Accessed 25 November 2026.
Figures to confirm before you act
- Reporting cycle: regulation 27 of GN No. 466 of 2025 says every year on Form No. 5; TISEZA's portal lists a bi-annual report and Invest Tanzania reported a quarterly notice (30 June 2026 deadline) not found on tiseza.go.tz. Confirm with TISEZA.
- Form No. 5 and its Second Schedule fee: not read; obtain the current form, the filing channel and the fee from TISEZA.
- The period TISEZA counts for the yearly report (certificate anniversary or financial year): not stated in regulation 27; confirm.
- Certificate thresholds: regulation 14 gives TZS 1,500,000,000 (foreign or joint venture) and TZS 150,000,000 (Tanzanian owned); USD 500,000 and USD 50,000 are the figures TISEZA staff quoted on 10 November 2026. Confirm the figure in use.
- Penalties in sections 45(3) and 46: TZS 5,000,000 to TZS 50,000,000 and TZS 2,000,000 to TZS 5,000,000 as read in the English translation; confirm against the Swahili text before relying on them.
- Zanzibar: the parent Act (Act No. 14 of 2018 on ZIPA's page, Act No. 10 of 2023 in L.N. 59 of 2025) and the annual licence cycle were not read in the Acts; take to an advocate.
- Worked example figures for Kibaha Packaging Limited (USD 2,400,000 project, USD 1,880,000 invested, TZS 2,600 per USD, 54 staff, 14 customs entries, TZS 290,000,000 relieved) are illustrative.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
Does a company that registered with the former Tanzania Investment Centre before July 2025 still have to file the report?
Yes. Section 51(2)(a) keeps a certificate of incentives issued under the repealed Tanzania Investment Act 2022 in force, and section 51(3) moves matters pending before the former Tanzania Investment Centre to TISEZA. The section 32 duties and the 24-month revocation ground attach to that certificate.
What happens if the project has not started yet?
File the report anyway. Land secured, permits in hand and capital on deposit are progress before construction. Section 17(2)(d) allows revocation where a project has not started within twelve months without valid reason, so the report is where the reason belongs.
Can the report be filed in Swahili or English?
The Regulations are published in Swahili and the Act has an English translation under GN No. 4 of 2026, so TISEZA works in both. The form governs. Keep the evidence file in the language of the documents themselves, since bank advices are not translated.
Should the capital invested figure be the amount spent or the amount committed?
Report cash spent and assets delivered by category, with orders placed shown separately as commitments. TISEZA's published quarterly figures are commitments at registration, so an officer wants the spent figure. A lender wants the same split for cost to complete.
Who signs the investment progress report?
A director, because section 45(3)(a) makes it an offence to knowingly or recklessly give false or misleading information and the signatory carries that exposure. The finance manager and project manager initial the pages they prepared, and the accountant signs a short reconciliation note.
Does the report replace the notice of changes under section 18?
No. Section 18 requires written notice when the investment ceases, passes to a successor, changes name or particulars, or expands. The report refers to the notice and its date. Section 18(3) lets an affected person notify TISEZA after six months if the investor fails to.
Is a zone licence holder on the same cycle as a certificate holder?
No. Regulation 41(1)(k) of GN No. 466 of 2025 requires a special economic zone operator to submit a quarterly implementation report, and regulation 36(1) requires a zone developer to file quarterly construction reports. A certificate holder outside a zone reports under regulation 27.
How does the report help a bank drawdown?
A lender funding against milestones reads the signed progress report as the record of what is in the ground. Where the report, the fixed asset register and the bank statements agree, the drawdown needs no further proof. Attach the report to each request.