- What the contract and the law say
- Who should read this
- What must a monthly progress report contain?
- How are planned and actual progress compared?
- Why does the lender read the financial section first?
- Worked example: a TZS 3,600,000,000 building at month 9
- Which regulators must the report feed, and when?
- Mainland and Zanzibar: which conditions apply?
- What to do now
- Key dates
- What the NEMBO desk prepares
- How Zatra helps
- Sources and status
- Frequently asked questions
What must a monthly project progress report in Tanzania contain?
A project progress report Tanzania works contracts require under PPRA sub-clause 4.21 goes to the Project Manager within seven days of each month end. It carries progress charts, photographs, plant and materials status, personnel and equipment, quality records, a notices register, environmental and safety metrics, and planned against actual progress with recovery measures. The financial section reconciles measured, certified and paid sums.

What the contract and the law say
A project progress report Tanzania contractors and consultants submit each month is a contractual deliverable before it is a courtesy. The PPRA General Conditions of Contract for Construction of Medium and Large Works (February 2022) require at sub-clause 4.21.1 a monthly progress report to the Project Manager in six copies. The first covers the period to the end of the first calendar month after the Commencement Date, and each later report is due within seven days after the period it covers. Sub-clause 4.21.3 lists the contents. They are charts and descriptions of progress, photographs, manufacturer details and key dates for main plant and materials, personnel and equipment records, and quality assurance documents and test results. They continue with a list of notices given under the claims clauses, environmental and social metrics, and a comparison of actual and planned progress with the events jeopardising completion and the measures to overcome delay.
The General Conditions of Contract for Small Works (February 2022) take a lighter route. Clause 36.1 requires the programme within the time in the special conditions. Clauses 36.2 and 36.3 require progress reports and an updated programme at the intervals the special conditions set, and let the Project Manager withhold a stated amount from the next certificate when the update is late. Clause 36.4 requires each revision to show the effect of variations and compensation events, and clause 36.5 adds the environmental and social metrics in Appendix A. Those conditions implement the Public Procurement Act, 2023, whose section 94 makes the user department responsible for quantity, quality, cost and time and has the appointed supervisor prepare implementation plans and reports. Section 95 limits amendments to 15 percent of the original contract sum without the budget approving authority and the Attorney General's vetting.
Four regulators read the same report for their own purposes. The Contractors Registration Board requires every project worth TZS 10,000,000 or more to be registered, with the sticker on the site board. The Occupational Health and Safety Act, 2003 requires the Chief Inspector to be notified within 24 hours of a death, a serious injury or a dangerous occurrence, with the prescribed form within seven days (section 101). The Workers' Compensation Regulations, 2016 require notice to the Fund within seven working days on Form WCN-1 (regulation 15). And the Environmental Impact Assessment and Audit Regulations, 2005 require an annual self-audit and report to the Council under regulation 50, with a control audit every five years under regulation 49. Zatra's note on building permits and construction approvals covers the approvals that come before the first report. This guide covers the report.
Who should read this
This guide is for the contractor's project manager, the consulting engineer who supervises, the quantity surveyor who values the work, and the client-side project coordinator in a ministry, agency, council or company. It also serves the finance team that must turn a progress report into a cash forecast, and the lender or donor project management unit that funds the works. The NEMBO note on the donor project report covers the narrative and financial file for grant-funded programmes.
What must a monthly progress report contain?
The Medium and Large Works list at sub-clause 4.21.3 is the fullest statement in a Tanzanian standard contract, and it matches FIDIC sub-clause 4.21 as summarised by Fenwick Elliott in 2018. The table maps each item to the clause that requires it and to the reader who acts on it.
| Section of the report | Required by | Who acts on it |
|---|---|---|
| Progress narrative by stage, with charts | GCC M&L 4.21.3(a); GCC SW 36.2 | Project Manager, client coordinator |
| Updated programme showing variations and compensation events | GCC SW 36.4; FIDIC 8.3 | Project Manager; extension of time decision under GCC SW 37 |
| Planned against actual, with recovery measures | GCC M&L 4.21.3(h) | Client, lender; liquidated damages under GCC SW 59 |
| Photographs, dated and located | GCC M&L 4.21.3(b) | Everyone who cannot visit the site |
| Plant and materials: orders, manufacture, shipping, delivery | GCC M&L 4.21.3(c) | Project Manager; advance recovery under GCC SW 61 |
| Personnel and equipment on site | GCC M&L 4.21.3(d) | Client; CAG tests key personnel against the bid |
| Quality: tests, material certificates, non-conformances | GCC M&L 4.21.3(e) | Supervising engineer; NEMC and TBS where relevant |
| Notices and claims register | GCC M&L 4.21.3(f); GCC SW 41 early warning | Project Manager; compensation events under GCC SW 55 |
| Environment, health and safety metrics | GCC M&L 4.21.3(g); GCC SW 36.5; OSHA s.101; WCF reg 15; EIA regs 50 | OSHA, WCF, NEMC, lender safeguards |
| Financial: statement of work done, certificates, retention, advance recovery, interest claims | GCC SW 52, 53, 58, 61 | Client finance, lender, contractor's bank |
| Variations and extension of time status | GCC SW 37, 50; PPA s.95 | Accounting officer; tender board above thresholds |
| Compliance: CRB sticker, ERB and AQRB supervision, subcontractor disclosure to TRA | Cap. 235; Finance Act 2026 | CRB inspectors; TRA |
The report that gets read is the one whose first page answers three questions in numbers: how far behind or ahead the works are, how much has been certified and paid against the contract sum, and what the client must decide this month. The chapters behind it carry the evidence.
How are planned and actual progress compared?
The comparison sub-clause 4.21.3(h) asks for is earned value by another name. The Project Management Institute defines planned value as the budgeted cost of work scheduled to date, earned value as the budgeted cost of work performed, and cost incurred as the third measure. Schedule variance is earned value less planned value, the schedule performance index is earned value divided by planned value, and an index at or above 1.0 is favourable. A Tanzanian works contract supplies the figures: the priced bill of quantities and the approved programme give planned value, the measured work in the monthly statement gives earned value, and the contractor's ledger gives actual cost.
The programme behind the comparison must be the one the Project Manager approved and must carry the effect of every variation and compensation event, or the comparison measures the contractor against a baseline the contract no longer recognises. Where the works are behind, the report states the cause, whether a claim notice has been given, and the recovery measures with their cost. Where the delay is the client's, the early warning under clause 41 of the small works conditions and the notice list under 4.21.3(f) are the record that supports an extension of time under clause 37, which the Project Manager decides within 21 days. The NEMBO note on the payment claim after contract signing covers the first certificates.
Why does the lender read the financial section first?
Because payment in Tanzanian public works is late more often than it is on time. The Controller and Auditor General's Annual General Report on the Audit of Development Projects for 2024/25, issued on 30 March 2026, found long-outstanding payment claims of TZS 81,790,000,000 with delays of 5 to 1,161 days and avoidable interest of TZS 8,230,000,000 across nine projects. It also found variations of TZS 66,080,000,000 approved without authorisation and payments of TZS 6,060,000,000 unsupported by measurement records. The same report cites the Medium and Large Works conditions at 14.7(c) and 14.8 for interest, compounded monthly, where the contractor is not paid within 56 days after the Engineer receives the statement. A 2022 National Audit Office performance audit found 89 of 156 interim payment certificates, 57 percent, paid late by 18 to 235 days.
The financial section therefore reconciles five numbers every month. The cumulative value of work measured. The cumulative value certified and the date of each certificate. The cumulative amount paid and the days from certificate to payment. Retention held, and advance recovered. Interest accrued on late certificates at the Bank of Tanzania rate prevailing at contract signature, which clause 53.1 of the small works conditions fixes as the rate. A donor project management unit adds its own clock: World Bank financing agreements for Tanzanian projects read for this guide require interim unaudited financial reports within 45 days after each calendar quarter, and an African Development Bank appraisal for a Tanzanian project required quarterly progress reports within 45 days of quarter end. The NEMBO note on the covenant compliance certificate covers the lender's own reporting form.
Worked example: a TZS 3,600,000,000 building at month 9
This worked example follows a 24-month office building contract for a public agency under the small works conditions, at month 9. Planned progress is 42 percent and measured progress is 36 percent. The special conditions set retention at 10 percent and the advance at 15 percent, the ceiling in the PPRA tender data sheet. Figures other than the contract rates are illustrative.
| Line | Computation | TZS |
|---|---|---|
| Contract sum | Accepted tender | 3,600,000,000 |
| Planned value at month 9 | 42 percent x 3,600,000,000 | 1,512,000,000 |
| Earned value at month 9 | 36 percent x 3,600,000,000 | 1,296,000,000 |
| Schedule variance | 1,296,000,000 less 1,512,000,000 | (216,000,000) |
| Schedule performance index | 1,296,000,000 / 1,512,000,000 | 0.857 |
| Cumulative gross certified | Certificates 1 to 8 | 1,180,000,000 |
| Measured but not yet certified | 1,296,000,000 less 1,180,000,000 | 116,000,000 |
| Retention, 10 percent of certified | GCC SW 58.1, subject to the cap | 118,000,000 |
| Advance paid at commencement | 15 percent x 3,600,000,000 | 540,000,000 |
| Advance recovered to date | 540,000,000 / 2,880,000,000 = 18.75 percent of certified value, to full recovery at 80 percent certified | 221,250,000 |
| Net certified before tax | 1,180,000,000 less 118,000,000 less 221,250,000 | 840,750,000 |
| VAT at 18 percent on the gross certificates | Each certificate a separate supply under VAT Act s.19 | 212,400,000 |
| VAT withheld by a government agent, 6 percent | F0233 | 70,800,000 |
| Income tax withheld on a Government contract | 2 percent of goods (F0223) or 5 percent of service fees (F0212); classification to confirm | 23,600,000 or 59,000,000 |
The report's first page states that the works are 6 percentage points behind programme, that the schedule performance index is 0.857, and that the recovery plan adds a second concrete gang at a cost the contractor bears unless a compensation event is accepted. The financial page states that certificate 7, dated 72 days ago, remains unpaid, and that interest at the Bank of Tanzania rate fixed at signature has accrued from day 29 under clause 53.1. The advance recovery line shows that TZS 318,750,000 remains to be recovered before 80 percent of the contract price is certified. Those three numbers are what the agency's accounting officer, the contractor's bank and the ministry's project unit each take from the report.
Which regulators must the report feed, and when?
The report is the source from which four statutory filings are made, and a project unit that keeps the two apart files late.
| Filing | Trigger and deadline | Legal basis | Fee or penalty |
|---|---|---|---|
| CRB project registration and sticker | Every project of TZS 10,000,000 or more, before works start; annual returns July to September | Contractors Registration Act Cap. 235 s.4(1)(s); CRB guidance | Engaging an unregistered contractor: 1 to 10 percent of contract value, minimum TZS 5,000,000 (s.25(4)); missing signboard TZS 500,000 (NEW-05-29) |
| OSHA incident notification | Death, serious injury or dangerous occurrence: notify within 24 hours, form within 7 days | OHS Act 2003 s.101 | Workplace registration nil since 2018 (NEW-04-40); annual inspection fee by band (F0442) |
| WCF accident notice | Within 7 working days on Form WCN-1 | Workers' Compensation Regulations 2016 reg 15 | Default fine up to TZS 500,000 (reg 60) |
| NEMC environmental self-audit | Annually during implementation; control audit every five years | EIA and Audit Regulations 2005 regs 49, 50 | Offences under reg 60 |
| TRA contractor and subcontractor disclosure | Within 30 days of each contract: name, address, TIN, value, period, scope, expected withholding | Tax Administration Act as amended by the Finance Act 2026, per EY's 17 July 2026 analysis | Penalties under TAA s.89 (NEW-02-06) |
| ERB and AQRB supervision | Registered engineer and quantity surveyor named on the project; ERB project fees by band | Engineers Registration Act; Cap. 269 s.23 | ERB design and supervision fees TZS 450,000 to 3,000,000 by project value (ERB registration overview) |
Zatra's notes on OSHA registration and environmental audits after the EIA certificate set out the filings in full. The point for the report is that the safety and environmental chapter should be written so that the OSHA, WCF and NEMC forms can be completed from it without a second site visit.
Mainland and Zanzibar: which conditions apply?
The PPRA conditions, the Public Procurement Act, 2023 and the Contractors Registration Board regime apply to Mainland projects. Zanzibar procures under its own law. The Bill published by the House of Representatives in November 2024 names the authority ZPPRA and makes the accounting officer responsible for contract administration at section 77. It caps variations at 25 percent at section 81 and requires quarterly and annual implementation reports to the authority at section 36. Its enactment status was not confirmed for this guide, and no Zanzibar standard works contract was found. A Zanzibar Contractors Registration Board exists, according to Daily News reporting of 2 August 2026, and Zanzibar projects fiscalise and pay VAT at 15 percent through ZRA (F0246). Take the conditions and the reporting clause from the Zanzibar contract itself, and route any dispute about payment or extension of time to an advocate admitted in Zanzibar.
What to do now
- Read the reporting clause. Find the progress report interval, the number of copies, the submission day and the withholding sanction in the general and special conditions, and put them in the project calendar.
- Baseline the programme. Have the Project Manager approve the programme and the method of measuring progress before the first report, and reissue it after every variation and compensation event.
- Fix the first page. Three numbers every month: schedule performance index, cumulative certified and paid against the contract sum, and the decisions needed from the client.
- Reconcile the money. Measured, certified, paid, retention, advance recovery and interest accrued, each with its date, tied to the certificates and the bank statement.
- Keep the notices register current. Every early warning and claim notice logged with its date, so the extension of time and compensation event record is already in the report.
- Write the safety and environment chapter to the forms. Incidents by OSHA category, WCF notices sent, NEMC conditions monitored, so each regulator's form is a copy exercise.
- Add the lender annex. Quarterly interim financial report within 45 days for a World Bank project, the financier's progress report format for a development bank, and the covenant certificate for a commercial lender.
Key dates
| Date or period | What happens | Source |
|---|---|---|
| End of the first calendar month after commencement | First monthly progress report period closes; report within 7 days | GCC M&L 4.21.1 |
| Within 28 days of the Letter of Acceptance | Performance security delivered | GCC M&L 4.2.2 |
| Monthly | Statement of work done submitted | GCC SW 52.1 |
| Within 28 days of the statement | Project Manager certifies | GCC SW 52.2 |
| Within 28 days of the certificate | Employer pays; interest at the BoT rate at signature thereafter | GCC SW 53.1 |
| 56 days after the Engineer receives the statement | Interest, compounded monthly, on Medium and Large Works contracts | GCC M&L 14.7(c), 14.8 as cited by the CAG |
| Within 21 days of a request | Project Manager decides an extension of time | GCC SW 37.2 |
| 24 hours and 7 days | OSHA incident notification and form | OHS Act 2003 s.101 |
| 7 working days | WCF accident notice on Form WCN-1 | WC Regulations 2016 reg 15 |
| Within 30 days of each contract | Contractor and subcontractor disclosure to TRA | Finance Act 2026, effective 1 July 2026 |
| 45 days after quarter end | Interim financial report to the World Bank; quarterly progress report to AfDB | Financing agreements read |
| July to September each year | CRB annual returns | CRB guidance |
| Annually; every five years | NEMC self-audit; control audit | EIA and Audit Regulations 2005 regs 49, 50 |
What the NEMBO desk prepares
NEMBO designs the monthly progress report as a controlled template: the three-number first page, the earned value chart, the programme comparison, the photograph log, the quality and safety registers, the financial reconciliation and the regulator annex, so that month 2 is produced by updating month 1. The set sits in the financial reports and CFO packs desk, is listed in the library, and sits beside the monthly management accounts pack, and it follows the document control rules in the NEMBO note on controlled documents and ISO 9001. Zatra Consultants prepares and checks the content: the clause map for the contract in hand, the certificate and payment reconciliation, the interest computation and the filing calendar. Every page of the finished work reads free online first, with a Customise for your brand option on the library page.
There are two cost buckets, kept separate on every quotation. Government charges are paid at the official rate to the authority: CRB registration and annual fees (F0528 to F0537), ERB project fees, OSHA inspection fees (F0442), NEMC audit fees and any penalty. NEMBO's and Zatra's fees are published on the pricing page and quoted in writing. NEMBO does not decide or guarantee any authority's outcome, and the same holds for any bank or tender panel. The process page sets out how a brief becomes a delivered template.
How Zatra helps
Zatra's business process and SOP service builds the reporting procedure, the measurement method and the approval workflow around the template, and its outsourced finance desk reconciles certificates to cash. The desk is led on systems, engineering and construction documents by Eng. Dennis Wilson, whose project record includes the MUHAS Academic Medical Centre construction. Claims for extension of time, interest on late payment and any dispute under the contract go to an advocate, as do adjudication and arbitration. Brief the desk through the start page, and read the NEMBO notes on the delegation of authority matrix and the tender price schedule for the documents on either side of the report.
Project report and CFO pack
Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.
Open the desk pageSources and status
Accurate as at 18 November 2026. The small works conditions were read to the end. The medium and large works conditions were readable to sub-clause 6.9, so the 56-day payment period and the interest clause at 14.7 and 14.8 are cited through the CAG report. Regulation 314 of the 2024 Regulations on payments was not readable, so no statutory payment period is stated. The Zanzibar procurement Bill's enactment was not confirmed. The worked example is illustrative except for the contract rates cited.
- 1General Conditions of Contract for Construction of Medium and Large Works, sub-clauses 4.2, 4.21Public Procurement Regulatory Authority, February 2022. Accessed 18 November 2026.
- 2General Conditions of Contract for Small Works, clauses 36, 37, 41, 50, 52, 53, 58, 59, 61Public Procurement Regulatory Authority, February 2022. Accessed 18 November 2026.
- 3Public Procurement Act, 2023, sections 93 to 98Public Procurement Regulatory Authority, English text GN 813 of 20 September 2024. Accessed 18 November 2026.
- 4Annual General Report on the Audit of Development Projects for the financial year 2024/25National Audit Office of Tanzania, 30 March 2026. Accessed 18 November 2026.
- 5What a contractor should do after being registeredContractors Registration Board, undated guidance read 18 November 2026. Accessed 18 November 2026.
- 6Occupational Health and Safety Act, 2003, sections 16, 17, 90, 92, 101TanzLII, Act No. 5 of 2003. Accessed 18 November 2026.
- 7Workers' Compensation Regulations, 2016, GN 185, regulations 13, 14, 15, 58, 60Parliament of Tanzania library copy, Gazette of 2016. Accessed 18 November 2026.
- 8Environmental Impact Assessment and Audit Regulations, 2005, GN 349, regulations 46, 49, 50, 52, 57FAOLEX copy of the 2005 Regulations. Accessed 18 November 2026.
- 9Disbursement and Financial Information Letter, Usangu Catchment projectWorld Bank, 27 February 2025. Accessed 18 November 2026.
- 10Earned value managementProject Management Institute, 31 August 2026. Accessed 18 November 2026.
- 11Some thoughts on how the 2017 FIDIC contract deals with timeFenwick Elliott, 1 March 2018. Accessed 18 November 2026.
- 12Tanzanian Finance Act 2026 analysis: contractor disclosure within 30 daysEY Global Tax News, 17 July 2026. Accessed 18 November 2026.
- 13Contractors push for timely payments to boost project deliveryDaily News, 2 August 2026. Accessed 18 November 2026.
Figures to confirm before you act
- The 56-day payment period and monthly compounded interest at sub-clauses 14.7(c) and 14.8 of the Medium and Large Works conditions: cited through the CAG report; read the contract's own clause.
- Regulation 314 of the Public Procurement Regulations, 2024 on payments to contractors: not readable; no statutory day count is stated here.
- Classification of works payments for income tax withholding, 2 percent as goods to Government (F0223) or 5 percent as service fees (F0212): confirm with TRA for the contract in hand.
- Whether VAT on a certificate is computed before or after retention and advance recovery: confirm with the client's accountant.
- Finance Act 2026 contractor and subcontractor disclosure: the section number in the Tax Administration Act was not read; EY's analysis is the source.
- Zanzibar Public Procurement Act (2024 Bill) enactment and the Zanzibar standard works contract: confirm with the Zanzibar authority.
- CRB project registration fee: no amount printed on the guidance read; take the CRB debit note.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
How often must a contractor report progress in Tanzania?
Monthly under the PPRA conditions for medium and large works, with each report due within seven days after the month it covers, in six copies to the Project Manager. Under the small works conditions the interval is set in the special conditions, and the Project Manager may withhold a stated sum from the next certificate when the updated programme is late.
What is the difference between a progress report and an interim payment certificate?
The progress report describes the state of the works and the programme. The interim payment certificate is the Project Manager's valuation of work done, issued within 28 days of the contractor's monthly statement under the small works conditions and paid within 28 days of its date. The report's financial section reconciles the two.
When does interest on late payment start?
Under the small works conditions, from the day after the 28-day payment period following the certificate, at the Bank of Tanzania rate prevailing at contract signature. The CAG cites the medium and large works conditions at 14.7(c) and 14.8 for interest compounded monthly after 56 days from the Engineer's receipt of the statement. Read the clause in the contract in hand.
What is a schedule performance index and why does the report show it?
Earned value divided by planned value. Earned value is the budgeted value of work done to date; planned value is the budgeted value scheduled to date. An index below 1.0 means the works are behind. It gives the employer, the lender and the project unit one number that the narrative then explains.
Who must be told about an accident on site?
OSHA's Chief Inspector within 24 hours for a death, serious injury or dangerous occurrence, with the prescribed form within seven days under section 101 of the 2003 Act. The Workers Compensation Fund within seven working days on Form WCN-1 under regulation 15 of the 2016 Regulations. The accident also goes in the site register and the report's safety chapter.
Does the client need to approve a variation before the work is done?
Under the small works conditions the Project Manager assesses a variation quotation within seven days and may use bill rates where they apply. Under the medium and large works conditions the Project Manager needs the Employer's approval before instructing a variation except in an emergency. Section 95 of the Act caps cumulative amendments at 15 percent without higher approval.
What does a donor project management unit add to the report?
Its own financial format and clock. World Bank financing agreements for Tanzanian projects require interim unaudited financial reports within 45 days after each quarter, and an African Development Bank appraisal required quarterly progress reports within 45 days. The unit also tests the environmental and social metrics in the report against the project's safeguard instruments.
Do the same conditions apply to a Zanzibar project?
No. Zanzibar procures under its own law, with a 2024 Bill published to replace the 2016 Act that names ZPPRA, caps variations at 25 percent and requires quarterly implementation reports. Its enactment was not confirmed for this guide and no Zanzibar standard works contract was found. Take the reporting clause from the Zanzibar contract itself.