- What the law says
- Who should read this
- What must the method statement contain?
- How must the work programme be built?
- What proof does the equipment schedule need?
- How does the panel read key personnel and CVs?
- Which plans and schedules complete the technical bid?
- How does a PPRA evaluation panel read the technical bid?
- Common faults and the fix for each
- Who prepares, reviews and signs the technical bid?
- Worked example: Dodoma Civil Works Limited, November 2026
- Mainland and Zanzibar: which rules differ?
- What to do now
- Key dates
- What the NEMBO desk prepares
- How Zatra helps
- Sources and status
- Frequently asked questions
What must the technical bid for a works tender in Tanzania contain?
The technical bid for a Tanzanian public works tender holds a method statement, a work programme within the contract period, an equipment schedule with proof of ownership or hire, and key personnel CVs with ERB registration. It also carries a past experience schedule, HSE and quality plans and a site organisation chart. The PPRA standard tendering documents call this the Technical Proposal and reject an unrealistic one.

What the law says
A method statement is the written account of how a contractor will build the works: the sequence, the resources, the temporary works and the controls. In a Tanzanian public works tender it sits inside the technical bid, next to the work programme, the equipment schedule, the key personnel CVs and the past experience schedule. The evaluation panel reads these before it reads the price.
The governing law on the Mainland is the Public Procurement Act, 2023 (Act No. 10 of 2023), assented to on 29 September 2023 and in force from 17 June 2024 under GN No. 455 of 7 June 2024, per PPRA's notice of 12 June 2024. Section 87(1) says "the basis for tender evaluation and selection of the successful tenderer shall be clearly specified in the tender document". Section 89(1) adds that the lowest submitted price "may not necessarily be the basis for selection". Section 55 provides for post-qualification of the lowest evaluated tenderer before award.
The Public Procurement Regulations, 2024 came into effect on 1 July 2024 (regulation 1). Regulation 7(5) requires evidence of "professional and technical capacity, adequacy of financial resources, equipment and other facilities" and "adequacy of personnel". Regulation 7(13)(c) lists "the major items of equipment proposed for use" and "the qualifications and experience of the key personnel" among the contents of a tender. Regulation 11(1) requires procurement to run through the electronic system, NeST.
The forms come from the PPRA Standard Tendering Document for Small Works (PPR/STD/W/SW/02/2022) and Standard Tendering Document for Medium and Large Works (PPRA/STD/W/ML/02/2022). In both, ITT 11.1(g) names the Technical Proposal as "a statement of work methods, equipment, personnel, schedule". Section IV asks the panel to assess the capacity to mobilise key equipment and personnel consistent with the proposed work methods and scheduling. ITT 28.9(d) lists an "unrealistic and inadequate technical proposal, implementation plans and schedules" as a ground for rejection. Both editions are dated February 2022; check for a later one before each bid.
Three other authorities stand behind the bid. The Contractors Registration Act (Cap. 235) makes unregistered contracting an offence, and section 10(3) provides for a certificate showing type, category and class. The Engineers Registration Board's registration page states that all persons practising engineering must register under Cap. 63. The Occupational Health and Safety Act, 2003 (Cap. 297) requires registration of a workplace before it operates (section 16(1)).
Who should read this
This guide is for the managing director, tender manager or contracts engineer of a registered contractor preparing a works bid through NeST, and for the consultant or joint venture partner supplying CVs and equipment proof. Suppliers of goods and consultancy firms can skip it; their forms are covered in tender evaluation criteria. Separate guides cover eligibility documents, qualification criteria, the price schedule and the securing declaration.
What must the method statement contain?
The method statement answers one question: does this contractor understand the works it has priced? The panel compares it with Section VII (drawings and specification), the programme and the priced bill.
Sequence and resources
Set out the works in build order, activity by activity, with the gang, the plant and the daily output assumed for each. Tie each activity to its bill item and its bar on the programme. State material sources: the borrow pit, the quarry, the water source and the haul distances behind the rates.
Temporary works and site establishment
Describe the camp, stores, laboratory, access roads, diversions and dewatering, and name who designs and checks temporary works.
Traffic and community management
For works on a live road, describe diversions, flagmen, signage, closures and liaison with the local authority and the police. Describe the grievance register, local labour recruitment and the code of conduct for personnel.
Environmental controls
Dust suppression, spoil disposal, borrow pit reinstatement, fuel and bitumen storage, waste handling and protection of watercourses belong here. Where the entity has identified environmental and social risks, the Small Works document asks for Management Strategies and Implementation Plans (TDS item 12). See the zatra.co guide to construction approvals.
Quality control and testing
List the tests the specification requires (compaction, CBR, gradation, concrete cubes, bitumen temperature), their frequency, the laboratory and who signs the certificates. State the hold points at which the project manager inspects before the next layer goes down.
How must the work programme be built?
The programme is a bar chart of the activities in the method statement, with start and finish dates, durations, the critical path and milestones. Under GCC clause 36.1 of the General Conditions of Contract for Small Works, the contractor submits a work programme for approval within the time stated in the special conditions, showing the methods, order and timing of activities. Clause 36.2 allows withholding from the next certificate if an updated programme is late.
Five tests the panel applies:
- The finish date falls on or before the Intended Completion Date. A programme longer than the contract period fails the critical work schedule test in ITT 28.8(e).
- Mobilisation is its own activity, covering site establishment, plant delivery and the performance security.
- The rainy season is allowed for: earthworks and gravel layers in a wet month either stop or carry lower outputs.
- Durations match the outputs in the method statement and the quantities in the bill.
- Milestones align with the interim certificates in the special conditions.
Consistency is the quiet test: the programme sets the timing, the price schedule sets the value of each activity, and the cash flow forecast (Form FIN-3.3) sets what the contractor funds before the first certificate. If the three disagree, the technical proposal is read as unrealistic.
What proof does the equipment schedule need?
Section IV 3.5 sets a table of "Equipment Type and Characteristics" against a "Minimum Number required". The panel checks that each item matches the characteristic asked for, that the number meets the minimum, and that the proof covers the whole contract.
| Status | Proof the panel accepts | What weakens it |
|---|---|---|
| Owned | Registration card in the company name; asset register line; valuation | Card in a director's name; no serial number; photo only |
| Hired | Signed hire agreement naming item, period and rate; dated availability letter | Undated quotation; agreement ending before completion |
| JV partner's plant | Partner's card plus a JV agreement clause committing the plant | Plant listed by both partners |
Give each item a line: type, make, capacity, year, registration or serial number, owned or hired, and the date it reaches site. The list must match the method statement and the fixed asset register.
How does the panel read key personnel and CVs?
Section IV 3.4 sets the key positions with "Total Work Experience (years)" and "In Similar Works Experience (years)". A CV that gives total years but not years on similar works fails the second column. Each CV carries the position proposed, qualifications with certificates, registration number, employment history and similar projects with values. The engineer signs it, the tenderer countersigns, and an availability declaration for the contract period is attached.
Registration matters on the Mainland. The ERB compliance page says engineering activities must be executed under the supervision of registered professional engineers, that firms must ensure all employed engineers are individually registered, and that its officers may inspect a site without notice. It cites the Engineering Works, Services and Projects Monitoring Regulations, 2015 (GN No. 237), whose regulations 21 and 26 set key staff requirements on road projects. The zatra.co guide to ERB registration for firms covers the firm side.
Under GCC clause 13.1 of the Small Works conditions, the contractor must employ the key personnel named in the Schedule of Key Personnel, and replacements need the project manager's approval.
Which plans and schedules complete the technical bid?
Past experience schedule
Forms EXP-4.1 and EXP-4.2(a) ask for general construction experience and for similar contracts of a minimum value completed since a stated year. Each line gives the contract, the employer, the role, the value, the dates and the certificate attached. The standard prequalification document treats a contract as substantially complete at 80 per cent or more of the works. The capability statement is the narrative version; the form is what scores.
Health, safety and environment plan
GCC clause 26.1 of the Small Works conditions requires all reasonable precautions for the health and safety of personnel and the public, in line with occupational health and safety law. The HSE plan tracks the duties in Cap. 297 as read on TanzLII. Workplace registration comes before operating (section 16(1)), with a compliance licence every twelve months (section 17(3)). Safety and health representatives are required where more than twenty people are employed (section 11(1)). Hazardous processes need an annual risk assessment (section 60), protective equipment (section 62) and instructed, supervised operators (section 34). Name the site safety officer, first aid and the accident register. See which workplaces must register with OSHA.
Quality plan and site organisation chart
GCC clause 4.9.1 of the General Conditions of Contract for Medium and Large Works requires a quality assurance system that demonstrates compliance with the contract. The quality plan names the quality manager, the inspection and test plan, the hold points and the non-conformance procedure; a contractor without ISO 9001 certification writes the procedure out, following the controlled documents guide. The site organisation chart is one page: head office line, site line from project manager to foremen, and the reporting line to the employer's project manager.
How does a PPRA evaluation panel read the technical bid?
The PPRA Guideline for Evaluation of Tenders in Procurement of Goods, Works and Non-Consultancy Services (GL/05/2020, effective 22 May 2020) sets the order. Preliminary examination removes incomplete, invalid or substantially non-responsive tenders; the guideline warns that "simple omissions or mistakes arguably occasioned by human error should not be grounds for rejection". Detailed evaluation follows: major deviations cause rejection, minor ones may be priced. The technical bid is therefore read twice: once for responsiveness and once for truth, when the committee may ask for original logbooks, call the employer named and check the ERB register. Section 88 keeps the evaluation confidential until the notice of intention to award, and section 69(4) gives five working days from that notice to lodge a complaint; see the PPAA appeal file guide.
On NeST, the PPRA Guidelines for Use of the National Electronic Procurement System (effective 30 July 2025) are clear. The system accepts no submission until every required field is answered, tenders open automatically at the deadline, and each user signs with a digital signature. See NeST registration and the tender file and the zatra.co guide to registering as a government supplier.
Common faults and the fix for each
| Fault | How the panel reads it | Fix |
|---|---|---|
| Generic method statement copied between bids | Unrealistic technical proposal | Rewrite per tender from the drawings and the site visit |
| Programme longer than the contract period | Cannot meet the critical work schedule | Resequence or add resources |
| Equipment listed without proof | Access not demonstrated | Attach card, hire agreement or availability letter per item |
| CV without ERB registration number | Key person cannot lawfully supervise | Register the engineer or propose a registered one |
| Same engineer in two concurrent bids | Availability declaration untrue | Keep a commitment register; name alternates |
| Programme, bill and cash flow disagree | Technical proposal inconsistent with pricing | Build all three from one activity list |
Who prepares, reviews and signs the technical bid?
The contracts engineer prepares the method statement and programme. The plant manager prepares the equipment schedule and its proof. Human resources collects CVs, certificates and availability declarations. The accountant reconciles the cash flow forecast with the programme and the price schedule. A second engineer reviews the method statement against Section VII. The managing director, or the attorney named in the power of attorney, signs each form, then signs digitally on NeST under the electronic signature workflow. One master file per tender, a version number on every page and a frozen copy of the upload are kept under the retention schedule.
Worked example: Dodoma Civil Works Limited, November 2026
Dodoma Civil Works Limited is an illustrative contractor registered with the Contractors Registration Board in Class Two, civil works. On 25 November 2026 it bids for the rehabilitation of 18 kilometres of district road at TZS 2,800,000,000 inclusive of VAT, with a 52-week contract period. All figures are illustrative. The company first confirms that this value is within its class limit on crb.go.tz. The programme treats the Dodoma rains from December to April as a planning assumption, so earthworks start in May.
| Milestone | Weeks | Planned value (TZS) | Cumulative |
|---|---|---|---|
| Mobilisation, camp, laboratory | 1 to 4 | 140,000,000 | 5 per cent |
| Site clearance and earthworks | 3 to 14 | 420,000,000 | 20 per cent |
| Culverts and drainage | 8 to 24 | 560,000,000 | 40 per cent |
| Sub-base and base course | 16 to 36 | 840,000,000 | 70 per cent |
| Double surface dressing | 34 to 46 | 616,000,000 | 92 per cent |
| Road furniture and markings | 44 to 50 | 112,000,000 | 96 per cent |
| Testing and taking over | 50 to 52 | 112,000,000 | 100 per cent |
The equipment schedule lists the Section IV 3.5 minimum items.
| Item | Number | Owned or hired | Proof attached |
|---|---|---|---|
| Motor grader, 140 kW | 1 | Owned | Registration card, 2026 valuation |
| Vibratory roller, 10 tonne | 2 | 1 owned, 1 hired | Card; 12-month hire agreement |
| Excavator, 20 tonne | 1 | Owned | Registration card |
| Tipper truck, 10 cubic metre | 6 | 4 owned, 2 hired | Four cards; hire agreement |
| Water bowser, 10,000 litre | 2 | Owned | Registration cards |
| Bitumen distributor and chip spreader | 1 each | Hired | Availability letter, weeks 34 to 46 |
| Concrete mixer, 500 litre | 2 | Owned | Purchase invoices |
The key personnel schedule names a project manager (Professional Engineer, 14 years, 9 on roads), a site agent (Professional Engineer, 9 years, 6 on roads), a materials engineer, a surveyor and a safety officer. Each CV carries an ERB number where applicable and an availability declaration. The cash flow forecast shows TZS 310,000,000 of own funds needed before the first certificate in week 8.
Mainland and Zanzibar: which rules differ?
The Public Procurement Act, 2023, the 2024 Regulations, PPRA, NeST and the PPAA apply to Mainland procuring entities. Zanzibar runs its own system. Its House of Representatives lists The Public Procurement Act, Act No. 2 of 2025. The Bill gazetted on 5 November 2024 proposed to repeal the Public Procurement and Disposal of Public Assets Act, No. 11 of 2016, establish a Zanzibar Public Procurement Regulatory Authority, and set a three working day complaint window. This post could not read the enacted text or confirm commencement; PPRA's news item of 9 February 2025 still names the Zanzibar Public Procurement and Disposal of Public Assets Authority (ZPPDA) as its counterpart. A contractor bidding in Zanzibar takes the current Act and bidding documents from ZPPDA and routes any dispute to an advocate in Zanzibar.
What to do now
- Read Section IV and Section VII first: list every minimum (personnel, equipment, experience, financial) and every works requirement.
- Visit the site and build one activity list: one list of quantities and outputs feeding the method statement, programme and cash flow.
- Write the method statement per tender: sequence, resources, temporary works, traffic and community management, environmental controls, quality control.
- Draw the programme inside the contract period: mobilisation, rainy season allowance, critical path, milestones aligned to interim certificates.
- Prove every machine: card, hire agreement or availability letter per item, reconciled to the fixed asset register.
- Clear every key person: ERB registration checked, certificates attached, availability declaration signed, commitment register updated.
- Assemble the plans: HSE plan reflecting Cap. 297 duties, quality plan, site organisation chart, experience schedule with certificates.
- Review, sign and upload: independent review, signature under the power of attorney, legible scans uploaded on NeST before the deadline.
Key dates
The tender validity period is set in the tender data sheet, and section 86 of the Act requires it to cover evaluation, approval, notification and signing. NeST registration is renewed every twelve months from payment of the registration fee, per the 2025 NeST guidelines; that fee and the tender participation fee are set by PPRA's fee schedule, see the Zatra government fees guide. CRB reviews permanent registration through annual return forms, and a Clyde & Co note of 7 February 2019 reports that a certificate is generally valid for one year. An ERB practising licence runs three years for a Professional Engineer. After award, the work programme is due within the period in the special conditions, and the project moves to the monthly progress report. The free tender evidence index tracks the expiry date of each certificate in the file.
What the NEMBO desk prepares
The NEMBO tendering desk designs and delivers the technical bid as one set: method statement, work programme with milestone table, equipment schedule with proof index, key personnel CVs, experience schedule, HSE and quality plans and site organisation chart, cross-referenced to the standard tendering document. Zatra Consultants prepares the content, and Dennis Wilson reviews engineering and construction documents before release. Two cost buckets apply: government, bank or regulator charges are paid at the official rate and are separate from NEMBO's and Zatra's fees, which are published on the packages page and quoted in writing. NEMBO does not decide or guarantee any authority's outcome. The client shares the details (the tender document, drawings, bill, plant list and CVs), and the process page shows the review and sign-off steps.
How Zatra helps
Zatra's tender and procurement advisory checks the technical bid against Section IV before upload, and its sector permits service handles the CRB, ERB and OSHA registrations behind the forms. The note on the Made in Tanzania procurement directive covers material sourcing. Read next the joint venture bid file and the project progress report. CPA Altho Mwangoa signs the audited figures and the cash flow forecast where a form requires an accountant's confirmation. Disputes, prosecutions, formal legal opinions and anything before a court, tribunal, the PPAA or a registry go to an advocate, as do all Zanzibar tender disputes.
Works tender technical bid set
Zatra Consultants prepares and checks the content on the details the Client shares. NEMBO designs and delivers it. Fees are published on the packages page and quoted in writing.
Open the desk pageSources and status
Accurate as at 25 November 2026. The Public Procurement Act, 2023 was read in part on ppra.go.tz, reaching sections 1 to 94. The Public Procurement Regulations, 2024 were read in part on mof.go.tz, reaching regulation 69. The PPRA standard tendering documents for works (February 2022) were read to Section IV; the Section V forms were not reached. The Zanzibar Act No. 2 of 2025 could not be read, so the 2024 Bill and the House listing were used; CRB and ERB details rest on the Boards' web pages and a Clyde and Co note of 2019.
- 1The Public Procurement Act, 2023 (Act No. 10 of 2023)PPRA, assented 29 September 2023, in force 17 June 2024 (GN No. 455 of 2024); English text GN No. 813 of 20 September 2024, read 25 November 2026. Accessed 25 November 2026.
- 2The Public Procurement Regulations, 2024Ministry of Finance, English version GN No. 261 published 25 April 2025, in effect 1 July 2024, read in part 25 November 2026. Accessed 25 November 2026.
- 3Standard Tendering Documents for Procurement of Small Works, National Competitive Tendering (PPR/STD/W/SW/02/2022)PPRA, February 2022, read in part 25 November 2026. Accessed 25 November 2026.
- 4Standard Tendering Documents for Procurement of Medium and Large Works (PPRA/STD/W/ML/02/2022)PPRA, February 2022, read in part 25 November 2026. Accessed 25 November 2026.
- 5General Conditions of Contract for Construction of Small Works (PPR/GCC/W/SW/02/2022)PPRA, February 2022, clauses 13, 21, 26, 36, 37 and 59 read 25 November 2026. Accessed 25 November 2026.
- 6Guideline for Evaluation of Tenders in Procurement of Goods, Works and Non-Consultancy Services (GL/05/2020)PPRA, effective 22 May 2020, read 25 November 2026. Accessed 25 November 2026.
- 7Guidelines for Use of the National Electronic Procurement System of Tanzania in Public Procurement and Supply Management, 2025PPRA, approved 29 July 2025, effective 30 July 2025, read 25 November 2026. Accessed 25 November 2026.
- 8Contractors Registration Act (Cap. 235)TanzLII, R.E. 2002 text as at 31 July 2002 (later amendments not applied), read 25 November 2026. Accessed 25 November 2026.
- 9Occupational Health and Safety Act, 2003 (Cap. 297)TanzLII, Act No. 5 of 2003 as at 11 April 2003, sections 3, 11, 13, 16, 17, 34, 60 and 62 read 25 November 2026. Accessed 25 November 2026.
- 10Registration Requirements for Firms Operating in the Tanzanian Construction IndustryClyde and Co (Peter Kasanda and Michaela Marandu) via Legal 500, 7 February 2019, read 25 November 2026. Accessed 25 November 2026.
Figures to confirm before you act
- Whether PPRA has issued an edition of the standard tendering documents for works later than February 2022 under the 2023 Act, and the Section V form names for personnel and equipment, which this post could not read.
- The GN number of the Public Procurement Regulations, 2024: the Ministry of Finance English version shows GN No. 261 published 25 April 2025 and lists GN Nos. 518 of 2024, 817 of 2024 and 42 of 2025 on its title page.
- The current CRB class limits per single contract (the 1999 by-laws figures on TanzLII are superseded) and whether a TZS 2,800,000,000 contract is within Class Two civil; the Board's current criteria booklet governs.
- The commencement date and text of the Zanzibar Public Procurement Act, No. 2 of 2025, the name of the Zanzibar regulator under it, and its complaint window (three working days in the 2024 Bill).
- The programme submission period after commencement (set in the special conditions under GCC 36.1), the tender validity period (tender data sheet), and the five working day complaint window in section 69(4).
- ERB practising licence periods (three years for a Professional Engineer, one year for a temporary registrant) as stated on erb.go.tz, and the key staff rules in regulations 21 and 26 of GN No. 237 of 2015.
- NeST registration renewal every twelve months from payment per the 2025 guidelines; the registration and tender participation fee amounts are set by PPRA's fee schedule (FEE NEEDED).
- All worked example figures for Dodoma Civil Works Limited (Class Two civil, TZS 2,800,000,000 price, 52 weeks, milestone values, equipment numbers, TZS 310,000,000 own funds) are illustrative.
This article is general information based on official sources available at the date of publication. It is not legal, tax or financial advice. Laws and notices change. Verify with the issuing authority or consult Zatra before acting.
Frequently asked questions
Can one method statement serve several lots in the same tender?
Only where the lots are the same type of work in the same place. Otherwise write a short lot-specific section covering access, material sources, programme and the plant and crew assigned, so the panel can see that resources are not double-counted across lots.
What happens if a key person leaves between bid and contract signing?
Tell the procuring entity in writing before signing and propose a replacement with equal or better qualifications, registration and similar works experience, with a CV and availability declaration. A substitution that lowers what the bid offered invites rejection at post-qualification.
Does the work programme need project management software?
No. A bar chart with activities, durations, dates, the critical path and milestones is enough for most works tenders. Software helps on larger contracts because the panel can see logic links and float. Export a legible PDF for NeST and keep the native file.
Can hired equipment count toward the minimum equipment list?
Yes, where the tender document asks for proof of access rather than ownership, which the standard documents do. The proof is a signed hire agreement naming the item, covering the contract period and dated for the tender. An undated quotation is read as no access.
Does a foreign engineer named as key personnel need ERB registration?
Yes. The Engineers Registration Board registers foreign applicants as Temporary Professional Engineers or Temporary Consulting Engineers, with an annually renewed licence. A foreign engineer without temporary registration cannot lawfully supervise engineering work on a Mainland site, so the CV should carry the temporary registration number.
Is an OSHA registration certificate needed at bid stage?
The site itself is registered before operating, after award. At bid stage the entity may ask for evidence that the company's existing workplaces are registered and hold a compliance licence, and the HSE plan should promise registration of the new site before work starts.
How should the technical bid respond to a clarification request?
Answer only the question asked, within the time given, without changing the price, the programme end date or the substance of the technical proposal. A clarification that adds equipment or personnel not in the original bid is a modification the panel cannot accept.
Does a joint venture submit one method statement or two?
One. The joint venture submits a single technical proposal that allocates activities to each partner, and the JV agreement commits each partner's plant and personnel to the contract. Experience and financial figures are evaluated per partner, but the method statement and programme are joint documents.